Exam 7: Scope Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The project scope statement establishes the project boundaries by stating what features and work elements are included (in scope)and which are excluded  (out of scope).

Free
(True/False)
4.9/5
(40)
Correct Answer:
Verified

True

By using a systematic process for creating a WBS,project team members can ensure that they include all deliverables that are required to be created.

Free
(True/False)
4.8/5
(37)
Correct Answer:
Verified

True

A "top-down" approach to creating a WBS is typically used when a project is unique and different from previous projects.

Free
(True/False)
4.9/5
(28)
Correct Answer:
Verified

False

The method of dividing the project scope into many parts that,when combined,would constitute the project deliverable is called _____: 

(Multiple Choice)
4.7/5
(37)

What are some of the benefits of creating a Work Breakdown Structure (WBS)?

(Essay)
4.7/5
(33)

The Work Breakdown Structure (WBS)is a framework that will be used as a basis for further planning activities including all the following EXCEPT:​ 

(Multiple Choice)
4.7/5
(39)

A WBS dictionary is a document that defines each of the terms used in the project scope statement.

(True/False)
4.8/5
(36)

The overall project is considered to be the first level of the WBS.All of the following methods can be used to organize the second level of the WBS EXCEPT:​ 

(Multiple Choice)
4.8/5
(33)

Explain how scope is defined on agile projects.

(Essay)
4.9/5
(35)

Work Breakdown Structures typically include one or more intermediate levels.Which of the following statements correctly describe the nature of these intermediate levels?​ 

(Multiple Choice)
4.9/5
(32)

The project scope refers to the features and functions of a project outcome such as a product,and,in some cases,service or result.

(True/False)
4.9/5
(27)

Since work packages provide the basis for future project planning activities,they should be as detailed as possible.

(True/False)
4.9/5
(27)

Baselining is defined as a method of dividing the project scope into many parts that,when combined,would constitute the project deliverable.

(True/False)
4.8/5
(39)

All of the following elements should be included in a project scope statement EXCEPT:​ 

(Multiple Choice)
4.8/5
(43)

On agile projects,the scope definition begins with :​ 

(Multiple Choice)
4.8/5
(38)

All of the following statements correctly describe a contemporary approach to create the Work Breakdown Structure (WBS)for a project EXCEPT:​ 

(Multiple Choice)
4.8/5
(33)

The project scope is the work that must be performed to deliver a product,service or result with the required features and functions.

(True/False)
4.9/5
(30)

When a project team needs to construct a WBS,it needs to include in its planning team a subject matter expert (SME)who understands how each segment of the work will be accomplished.

(True/False)
4.9/5
(38)

The priority of the product in agile is more significant than in traditional project management,as the outcome,or product,will drive the elaboration of the project.

(True/False)
4.9/5
(30)

While many projects may have a primary deliverable such as a house,almost all projects have additional deliverables such as documentation and customer support.

(True/False)
4.9/5
(32)