It is important to assign a unique name and a unique number to every component in the project Work Breakdown Structure.

(True/False)
4.8/5
(34)

Organizing the second level of the Work Breakdown Structure by major design components facilitates rolling wave planning.

(True/False)
4.9/5
(37)

Failure to include project management in the WBS will increase the likelihood that the project will not be completed on time and within budget.

(True/False)
4.8/5
(40)

The project scope planning processes include all of the following EXCEPT: 

(Multiple Choice)
4.7/5
(39)

Plan scope management is the process of creating a project scope statement.

(True/False)
4.7/5
(41)

Define Scope is the process of developing the:​ 

(Multiple Choice)
4.9/5
(31)

A _______ is the approved project plan mainly consisting of scope,schedule,and cost that is not normally altered unless a  formal change control request is approved for modifying these plans.​ 

(Multiple Choice)
4.9/5
(37)

A deliverable is a condition or capability needed by a user to solve a problem or achieve an objective that satisfies a standard,a specification,or any other formally documented need.

(True/False)
4.9/5
(30)

Which of the following statements concerning work packages is NOT correct?​ 

(Multiple Choice)
4.7/5
(43)

Which of the information below would NOT typically be included in the WBS dictionary for a specific work package?​ 

(Multiple Choice)
4.9/5
(39)

It is helpful to list requirements and supporting information in a requirements traceability matrix.When requirements are complete,they should meet all of these criteria EXCEPT:​ 

(Multiple Choice)
4.8/5
(40)

A _________ is a written request or formal proposal to propose changes to any project planning component such as a document,project deliverable,or baseline (scope,cost,and time).​ 

(Multiple Choice)
4.8/5
(33)

Identify and describe the three steps that the team should follow in order to define project scope and create a project scope statement.

(Essay)
4.7/5
(41)

If a problem occurs during project execution,the WBS is helpful in understanding exactly where and why the problem occurred.

(True/False)
4.7/5
(27)

A WBS component is a work element that is part of the WBS at any level.

(True/False)
4.8/5
(33)

Once the plan baseline has been approved and the project is underway,project teams deal with change by establishing and using a change control system to receive and review change proposals and accept or reject them after evaluating their impact on project scope,cost and schedule.

(True/False)
4.8/5
(31)

A typical change request form will include which of the following content items?​ 

(Multiple Choice)
4.8/5
(30)

Which of the following items best describes a project Work Breakdown Structure (WBS)?​ 

(Multiple Choice)
4.7/5
(39)

Which of the following is NOT a format that is typically used to represent a Work Breakdown Structure?​ 

(Multiple Choice)
4.9/5
(39)

This technique is an iterative process that identifies and defines the work to be completely accomplished in the near term,and plans the future work at a higher level.

(Multiple Choice)
4.8/5
(38)
Showing 21 - 40 of 44