Exam 7: Scope Planning
Exam 1: Introduction to Project Management49 Questions
Exam 2: Project Selection and Prioritization52 Questions
Exam 3: Chartering Projects39 Questions
Exam 4: Organizational Capability: Structure, Culture and Roles50 Questions
Exam 5: Leading and Managing Project Teams46 Questions
Exam 6: Stakeholder Analysis and Communication Planning46 Questions
Exam 7: Scope Planning44 Questions
Exam 8: Scheduling Projects56 Questions
Exam 9: Resourcing Projects45 Questions
Exam 10: Budgeting Projects46 Questions
Exam 11: Project Risk Planning45 Questions
Exam 12: Project Quality Planning and Project Kick-Off45 Questions
Exam 13: Project Supply Chain Management45 Questions
Exam 14: Determining Project Progress and Results44 Questions
Exam 15: Finishing the Project and Realizing the Benefits30 Questions
Select questions type
It is important to assign a unique name and a unique number to every component in the project Work Breakdown Structure.
(True/False)
4.8/5
(34)
Organizing the second level of the Work Breakdown Structure by major design components facilitates rolling wave planning.
(True/False)
4.9/5
(37)
Failure to include project management in the WBS will increase the likelihood that the project will not be completed on time and within budget.
(True/False)
4.8/5
(40)
The project scope planning processes include all of the following EXCEPT:
(Multiple Choice)
4.7/5
(39)
Plan scope management is the process of creating a project scope statement.
(True/False)
4.7/5
(41)
A _______ is the approved project plan mainly consisting of scope,schedule,and cost that is not normally altered unless a formal change control request is approved for modifying these plans.
(Multiple Choice)
4.9/5
(37)
A deliverable is a condition or capability needed by a user to solve a problem or achieve an objective that satisfies a standard,a specification,or any other formally documented need.
(True/False)
4.9/5
(30)
Which of the following statements concerning work packages is NOT correct?
(Multiple Choice)
4.7/5
(43)
Which of the information below would NOT typically be included in the WBS dictionary for a specific work package?
(Multiple Choice)
4.9/5
(39)
It is helpful to list requirements and supporting information in a requirements traceability matrix.When requirements are complete,they should meet all of these criteria EXCEPT:
(Multiple Choice)
4.8/5
(40)
A _________ is a written request or formal proposal to propose changes to any project planning component such as a document,project deliverable,or baseline (scope,cost,and time).
(Multiple Choice)
4.8/5
(33)
Identify and describe the three steps that the team should follow in order to define project scope and create a project scope statement.
(Essay)
4.7/5
(41)
If a problem occurs during project execution,the WBS is helpful in understanding exactly where and why the problem occurred.
(True/False)
4.7/5
(27)
A WBS component is a work element that is part of the WBS at any level.
(True/False)
4.8/5
(33)
Once the plan baseline has been approved and the project is underway,project teams deal with change by establishing and using a change control system to receive and review change proposals and accept or reject them after evaluating their impact on project scope,cost and schedule.
(True/False)
4.8/5
(31)
A typical change request form will include which of the following content items?
(Multiple Choice)
4.8/5
(30)
Which of the following items best describes a project Work Breakdown Structure (WBS)?
(Multiple Choice)
4.7/5
(39)
Which of the following is NOT a format that is typically used to represent a Work Breakdown Structure?
(Multiple Choice)
4.9/5
(39)
This technique is an iterative process that identifies and defines the work to be completely accomplished in the near term,and plans the future work at a higher level.
(Multiple Choice)
4.8/5
(38)
Showing 21 - 40 of 44