Exam 16: Managing Service Projects
Exam 1: The Service Economy50 Questions
Exam 2: Service Strategy70 Questions
Exam 3: New Service Development48 Questions
Exam 4: The Service Encounter50 Questions
Exam 5: Supporting Facility and Process Flows46 Questions
Exam 6: Service Quality42 Questions
Exam 7: Process Improvement27 Questions
Exam 8: Service Facility Location40 Questions
Exam 9: Service Supply Relationships51 Questions
Exam 10: Globalization of Services40 Questions
Exam 11: Managing Capacity and Demand47 Questions
Exam 12: Managing Waiting Lines34 Questions
Exam 13: Capacity Planning and Queuing Models46 Questions
Exam 14: Forecasting Demand for Services40 Questions
Exam 15: Managing Service Inventory40 Questions
Exam 16: Managing Service Projects40 Questions
Select questions type
The critical path for a project with uncertain activity times is not known for certain until after the project is completed.
(True/False)
4.9/5
(43)
The four sequential stages of team development include all of the following, except ________.
(Multiple Choice)
4.8/5
(44)
A major assumption in project network analysis is that sufficient resources are available to perform many activities concurrently.
(True/False)
5.0/5
(39)
Merge node bias occurs where the project network contains non-critical paths with small total slack times.
(True/False)
4.7/5
(36)
The term 'calendar' is used in project management to keep track of the days and hours required for completion of projects.
(True/False)
4.7/5
(35)
When crashing activities for construction projects, the contractor's minimum cost duration might not coincide with the client's target completion date.
(True/False)
5.0/5
(41)
The term 'total slack' refers to the amount of time an activity can be delayed without delaying the start of a subsequent activity.
(True/False)
4.8/5
(29)
Which of the following is not considered a source of unexpected project management problems?
(Multiple Choice)
4.9/5
(43)
Implementing critical path analysis is faced with all of the following problems, except ________.
(Multiple Choice)
4.9/5
(38)
A project history report should include all of the following items, except ________.
(Multiple Choice)
4.9/5
(33)
A resource-leveled schedule would have all of the following characteristics except ________.
(Multiple Choice)
4.8/5
(29)
For a project with uncertain activity times, the probability of project completion exceeding the expected time calculated for the critical path is ________.
(Multiple Choice)
4.9/5
(38)
Which one of the following is not an objective of activity crashing?
(Multiple Choice)
4.9/5
(43)
The amount of time an activity can be delayed without delaying the completion of the project is referred to as ________.
(Multiple Choice)
4.7/5
(34)
The single important attribute of a project manager is leadership ability.
(True/False)
4.8/5
(40)
The Beta distribution is useful in network analysis because it ________.
(Multiple Choice)
4.8/5
(41)
Which one of the following allows the manager to make probability statements with regard to meeting project objectives?
(Multiple Choice)
4.8/5
(27)
A major weakness with project completion time analysis with uncertain activity times is the ________.
(Multiple Choice)
4.7/5
(37)
Which of the following makes performance a source of unexpected project management problem?
(Multiple Choice)
4.8/5
(38)