Exam 7: Work Design and Measurement
Exam 1: Introduction to Operations Management70 Questions
Exam 2: Competitiveness, Strategy, and Productivity73 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design77 Questions
Exam 5: Strategic Capacity Planning for Products and Services103 Questions
Exam 6: Process Selection and Facility Layout151 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 11: Aggregate Planning and Master Scheduling81 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management162 Questions
Exam 14: Jit and Lean Operations88 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming105 Questions
Exam 20: Extension 4: Reliability10 Questions
Exam 21: Extension 5: Decision Theory126 Questions
Exam 22: Extension 7: Learning Curves68 Questions
Exam 23: Extension 8: The Transportation Model20 Questions
Exam 24: Extension 10: Acceptance Sampling65 Questions
Exam 25: Extension 14: Maintenance38 Questions
Select questions type
The methods analysis chart which describes the movements of both hands at the same time is a:
Free
(Multiple Choice)
4.7/5
(38)
Correct Answer:
D
What is the observed time (OT) for this task?
Free
(Multiple Choice)
4.9/5
(40)
Correct Answer:
A
Which of the following is not generally considered an advantage of specialization?
Free
(Multiple Choice)
5.0/5
(38)
Correct Answer:
D
A work sampling study of dockworkers must be set up.There will be a large number of random observations.However, for this exercise, determine an observation schedule (arranged chronologically) for six observations.Assume workers are on the docks for eight hours a day, and that the study will be done over a 60-day period.Use the random digits listed below.
(Essay)
4.9/5
(43)
If the person observed worked at a pace that is 80 percent of normal, what should be the normal time for this task?
(Short Answer)
4.9/5
(33)
A worker-machine chart can be used to determine how many machines an operator can manage.
(True/False)
4.8/5
(31)
The most widely used method of work measurement is work sampling.
(True/False)
4.8/5
(34)
Increasing compensation is always a way to improve worker satisfaction.
(True/False)
4.8/5
(29)
If the person observed worked at a pace that is 20 percent faster than average, what should be the normal time for this task?
(Short Answer)
4.9/5
(42)
What is the normal time (NT) for this task if the employee worked at a twenty-percent faster pace than is average?
(Multiple Choice)
4.9/5
(38)
Which of the following concerns is not one that job designers focus on?
(Multiple Choice)
4.8/5
(33)
Which of the following is not characteristic of time-based compensation plans?
(Multiple Choice)
4.8/5
(33)
Which of the following is not an advantage of work sampling compared to stopwatch time study?
(Multiple Choice)
4.9/5
(31)
How many observations should be made if he wants to be 95.44 percent confident that the maximum error in the observed time is one second?
(Multiple Choice)
4.9/5
(32)
Predetermined time standards involve the use of published data regarding how long various activities are expected to take.
(True/False)
4.8/5
(30)
What is the standard time (ST) for this task if the employee worked at a twenty percent faster pace than is average, and an allowance of twenty-five percent of job time is used?
(Multiple Choice)
4.9/5
(29)
The technique which can be used to estimate the percentage of time a worker or piece of equipment is idle is known as:
(Multiple Choice)
4.9/5
(34)
Showing 1 - 20 of 151
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)