Exam 14: Project Closure

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which of the following is NOT a role of the closure facilitator?

Free
(Multiple Choice)
4.8/5
(29)
Correct Answer:
Verified

D

__________ represent an analysis carried out during and shortly after the project life cycle;they attempt to capture positive and negative project learning.

Free
(Short Answer)
4.9/5
(39)
Correct Answer:
Verified

Lessons learned
Explanation: Lessons learned represent an analysis carried out during and shortly after the project life cycle;they attempt to capture positive and negative project learning.That is,"what worked and what didn't?"

The retrospective facilitator should be able to deliver bad news to the project sponsor or senior management without recriminations.

Free
(True/False)
4.9/5
(34)
Correct Answer:
Verified

True

The purpose of project evaluation is to assess how well

(Multiple Choice)
4.7/5
(30)

Identify three reasons it is important to use an independent facilitator to collect and implement lessons learned to improve management of current and future projects.

(Not Answered)
This question doesn't have any answer yet
Ask our community

Which of the following would NOT be appropriate to assess when evaluating team performance?

(Multiple Choice)
4.7/5
(33)

When a project is completed early with some parts of the project eliminated this is known as _________ project closure.

(Short Answer)
4.8/5
(32)

Before an evaluation of the project team can be effective and useful,a minimum core of conditions needs to be in place before the project begins.Which of the following would NOT be one of those conditions?

(Multiple Choice)
4.8/5
(32)

When the review group recommends methods for bringing final closure to a project that never seems it will end,this is an example of a ________ project closure.

(Short Answer)
4.8/5
(26)

Projects in process may need to be altered or canceled.Thus,a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change.This is called __________ project closure.

(Short Answer)
5.0/5
(39)

Identify and briefly describe four out of the five most common classifications for the way that projects end.

(Not Answered)
This question doesn't have any answer yet
Ask our community

A ____________ project closure is usually easy to identify and easy for a review group to close down.

(Short Answer)
4.9/5
(36)

The processes for capturing lessons learned continue to evolve,but there are still barriers to effectively mining lessons learned.

(True/False)
4.9/5
(33)

Why would a manager begin the evaluation process by asking the individual to evaluate his or her contributions to the project?

(Not Answered)
This question doesn't have any answer yet
Ask our community

Which of the following is NOT a wrap-up closure activity that might be found on a checklist?

(Multiple Choice)
4.7/5
(37)

When a project starts as a high priority but its rank erodes or crashes during its project life cycle resulting in closure of the project,this is an example of changed priority project closure.

(True/False)
4.8/5
(32)

Within the final report,a summary that simply highlights the key findings and facts relating to project implementation is called the ___________.

(Short Answer)
4.8/5
(30)

Which part of the final report presents major improvement actions that should be made?

(Multiple Choice)
4.9/5
(34)

A 360-degree performance evaluation includes feedback from peers,project managers,subordinates,and even customers.

(True/False)
4.9/5
(41)

During the closing phase,the project manager's challenge is to keep the project team focused on the remaining project activities and delivery to the customer until the project is complete.

(True/False)
4.9/5
(29)
Showing 1 - 20 of 88
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)