Exam 6: Developing a Project Plan

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The ________ calculates the earliest times that activities can start or finish.

Free
(Short Answer)
4.8/5
(20)
Correct Answer:
Verified

forward pass
Explanation: The forward pass describes how soon the activity can start (early start-ES)and how soon the activity can finish (early finish-EF).

An activity that has more than one dependency arrow flowing into it is termed a(n)

Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
Verified

D

Which of the following can be used without coordinating with managers of succeeding activities?

Free
(Multiple Choice)
4.9/5
(28)
Correct Answer:
Verified

B

In the network computation process what is a forward pass and what three things does it determine?

(Not Answered)
This question doesn't have any answer yet
Ask our community

Concurrent engineering,which has dramatically reduced the development time for new products,relies on what kind of lag?

(Multiple Choice)
4.9/5
(27)

A sequence of connected,dependent activities is termed a(n)

(Multiple Choice)
4.9/5
(39)

Activities that can take place at the same time if the manager wishes them to are called ________ activities.

(Short Answer)
4.9/5
(36)

A(n)________ activity has more than one successor activity.

(Short Answer)
4.8/5
(37)

The ________ calculates the critical path and determines how long an activity can be delayed without delaying the project.

(Short Answer)
4.9/5
(30)

Which of the following correctly calculates the early finish for an activity?

(Multiple Choice)
4.9/5
(27)

The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project.

(True/False)
4.8/5
(29)

Gantt charts are popular because they represent an easy-to-understand,clear picture on a time-scaled horizon.

(True/False)
4.7/5
(32)

Information to develop a project network is collected from the

(Multiple Choice)
4.9/5
(34)

In the network computation process what is a backward pass and what four things does it determine?

(Not Answered)
This question doesn't have any answer yet
Ask our community

Different activities along the same path can have different total slack.

(True/False)
4.9/5
(42)

System documentation cannot end until three days after testing has started.This is an example of which kind of lag?

(Multiple Choice)
4.7/5
(36)

Which of the following is provided by both the project network and the work breakdown structure?

(Multiple Choice)
4.9/5
(30)

The amount of time an activity can be delayed and yet not delay the project is termed

(Multiple Choice)
4.9/5
(27)

Which of the following is true about hammock activities?

(Multiple Choice)
4.7/5
(37)

A network has only one critical path and the slack for noncritical activities is high.This network would appear to have a _______ level of sensitivity

(Short Answer)
4.7/5
(38)