Exam 6: Developing a Project Plan
Exam 1: Modern Project Management88 Questions
Exam 2: Organization Strategy and Project Selection87 Questions
Exam 3: Organization: Structure and Culture90 Questions
Exam 4: Defining the Project89 Questions
Exam 5: Estimating Project Times and Costs91 Questions
Exam 6: Developing a Project Plan94 Questions
Exam 7: Managing Risk86 Questions
Exam 8: Scheduling Resources and Costs91 Questions
Exam 9: Reducing Project Duration94 Questions
Exam 10: Leadership: Being an Effective Project Manager88 Questions
Exam 11: Managing Project Teams94 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations94 Questions
Exam 13: Progress and Performance Measurement and Evaluation88 Questions
Exam 14: Project Closure88 Questions
Exam 15: International Projects95 Questions
Exam 16: Oversight86 Questions
Exam 17: An Introduction to Agile Project Management86 Questions
Exam 18: Project Management Career Paths35 Questions
Select questions type
The ________ calculates the earliest times that activities can start or finish.
Free
(Short Answer)
4.8/5
(20)
Correct Answer:
forward pass
Explanation: The forward pass describes how soon the activity can start (early start-ES)and how soon the activity can finish (early finish-EF).
An activity that has more than one dependency arrow flowing into it is termed a(n)
Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
D
Which of the following can be used without coordinating with managers of succeeding activities?
Free
(Multiple Choice)
4.9/5
(28)
Correct Answer:
B
In the network computation process what is a forward pass and what three things does it determine?
(Not Answered)
This question doesn't have any answer yet
Concurrent engineering,which has dramatically reduced the development time for new products,relies on what kind of lag?
(Multiple Choice)
4.9/5
(27)
Activities that can take place at the same time if the manager wishes them to are called ________ activities.
(Short Answer)
4.9/5
(36)
The ________ calculates the critical path and determines how long an activity can be delayed without delaying the project.
(Short Answer)
4.9/5
(30)
Which of the following correctly calculates the early finish for an activity?
(Multiple Choice)
4.9/5
(27)
The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project.
(True/False)
4.8/5
(29)
Gantt charts are popular because they represent an easy-to-understand,clear picture on a time-scaled horizon.
(True/False)
4.7/5
(32)
Information to develop a project network is collected from the
(Multiple Choice)
4.9/5
(34)
In the network computation process what is a backward pass and what four things does it determine?
(Not Answered)
This question doesn't have any answer yet
Different activities along the same path can have different total slack.
(True/False)
4.9/5
(42)
System documentation cannot end until three days after testing has started.This is an example of which kind of lag?
(Multiple Choice)
4.7/5
(36)
Which of the following is provided by both the project network and the work breakdown structure?
(Multiple Choice)
4.9/5
(30)
The amount of time an activity can be delayed and yet not delay the project is termed
(Multiple Choice)
4.9/5
(27)
A network has only one critical path and the slack for noncritical activities is high.This network would appear to have a _______ level of sensitivity
(Short Answer)
4.7/5
(38)