Exam 7: Managing Risk

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which of the following is NOT one of the potential responses to a specific risk event?

Free
(Multiple Choice)
4.7/5
(32)
Correct Answer:
Verified

C

An uncertain event or condition that,if it occurs,has a positive or negative effect on project objectives is termed a

Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
Verified

C

Identify and briefly describe the four steps in the risk management process.

Free
(Not Answered)
This question doesn't have any answer yet
Ask our community

Adopting proven technology instead of experimental technology is an example of mitigating a risk.

(True/False)
4.8/5
(36)

One common mistake that is made early on in the risk identification process is to focus on consequences and not on the events that could produce consequences.

(True/False)
4.9/5
(36)

Flooding would be devastating to the project;however,it is very unlikely.The project manager is most likely to __________ this risk.

(Short Answer)
4.8/5
(37)

Enhancing a risk is a tactic that seeks to eliminate the uncertainty associated with an opportunity to ensure that it definitely happens.

(True/False)
4.9/5
(31)

The chances of a risk event occurring as a project proceeds through its life cycle tend to

(Multiple Choice)
4.8/5
(35)

The significance of a risk is assessed in terms of the ________ and the impact of the event.

(Short Answer)
4.8/5
(38)

The risk associated with the unlikelihood that one of the key members will be struck by lightning would most likely be handled by which of the following?

(Multiple Choice)
4.8/5
(36)

Risks are evaluated in terms of

(Multiple Choice)
4.8/5
(32)

According to the Failure Mode and Effects Analysis (FMEA),Impact x Probability x Detection = __________.

(Short Answer)
4.9/5
(32)

Performance bonds,warranties,and guarantees are financial instruments used to share risk.

(True/False)
4.8/5
(27)

An uncertain event or condition that,if it occurs,has a positive or negative effect on project objectives is known as a __________.

(Short Answer)
4.8/5
(30)

The cost impact of a risk event occurring as a project proceeds through its life cycle tends to

(Multiple Choice)
4.8/5
(33)

Identify and briefly describe the four ways to respond to identified risks.

(Not Answered)
This question doesn't have any answer yet
Ask our community

Based on the following,which event should you be most concerned about? Based on the following,which event should you be most concerned about?

(Multiple Choice)
4.8/5
(32)

________ reserves are controlled by the project manager and the owner of the project and are used to cover major unforeseen risks to the entire project.

(Short Answer)
4.7/5
(33)

_____________ systems involve reporting,controlling,and recording changes to the project baseline.

(Short Answer)
4.8/5
(34)

The project being delayed is an example of a major risk that should be assessed.

(True/False)
4.9/5
(40)
Showing 1 - 20 of 86