Exam 13: Sales and Operations Planning
Exam 1: Introduction to Managing Operations Across the Supply Chain40 Questions
Exam 2: Operations and Supply Chain Strategy23 Questions
Exam 3: Managing Processes and Capacity28 Questions
Exam 4: Product Process Innovation55 Questions
Exam 5: Manufacturing and Service Process Structures40 Questions
Exam 6: Managing Quality35 Questions
Exam 7: Managing Inventories35 Questions
Exam 8: Lean Systems30 Questions
Exam 9: Customer Service Management57 Questions
Exam 10: Sourcing and Supply Management60 Questions
Exam 11: Logistics Management48 Questions
Exam 12: Demand Planning: Forecasting and Demand Management34 Questions
Exam 13: Sales and Operations Planning48 Questions
Exam 14: Materials and Resource Requirements Planning35 Questions
Exam 15: Project Management32 Questions
Exam 16: Sustainable Operations Management preparing for the Future30 Questions
Exam 17: Process Mapping and Analysis40 Questions
Exam 18: Quality Improvement Tools48 Questions
Exam 19: Advanced Methods for Project Scheduling30 Questions
Select questions type
A master production schedule shows the beginning inventory is 40 units, the forecast is 100 units and actual customer orders are 80 units.What is the quantity that is available to promise in period 1?
Free
(Multiple Choice)
4.9/5
(43)
Correct Answer:
D
The available capacity of a worker, machine, work center or facility during a specific period of time is compared against the capacity needed for a specific work schedule in a:
Free
(Multiple Choice)
4.9/5
(50)
Correct Answer:
A
Planning for which of the following products would see the LEAST benefit from the use of an MRP system?
(Multiple Choice)
4.8/5
(34)
The following table shows capacity requirements data for making Blodgetts.
A load profile would show:

(Multiple Choice)
4.8/5
(35)
Significant changes in an MPS quantity several weeks into the planning horizon can:
(Multiple Choice)
4.9/5
(39)
Constant changing of the master schedule and the resulting changes in the requirements for components is referred to as:
(Multiple Choice)
4.9/5
(29)
Jones Company uses widgets as component parts.In a particular week it has gross requirements for 250 units of widgets, beginning inventory of 50 widgets, and scheduled receipts of 350 widgets.Available inventory for the next period is:
(Multiple Choice)
4.9/5
(32)
MRP is a process that would be most applicable in which situation?
(Multiple Choice)
4.9/5
(39)
A master production schedule shows the beginning inventory is 50 units, the forecast is 80 unitsand actual customer orders are 70 units.Using a lot-for-lot rule, what is the MPS quantity for period 1?
(Multiple Choice)
4.8/5
(42)
An MRP record for a motor is shown in the following table.
What is the planned order release for week 4?

(Multiple Choice)
5.0/5
(37)
Zanda Company is looking for a requirements planning system to help plan replenishment of its finished goods throughout its network of distribution centers.The type of system Zanda should consider is known as:
(Multiple Choice)
4.9/5
(38)
A master production schedule shows the following information:
Using a lot-for-lot rule, what is the MPS quantity for period 1?

(Multiple Choice)
4.9/5
(50)
The planned order releases in week 5 are 100 units.Each unit must be processed for 5 minutes at the work station.If the available capacity at the work station is one hour:
(Multiple Choice)
4.8/5
(27)
Software that consolidates all of the business planning systems and data throughout an organization is:
(Multiple Choice)
4.7/5
(40)
If the cumulative lead time is 8 weeks, to be feasible the MPS planning horizon must be:
(Multiple Choice)
5.0/5
(43)
Which of the following information is NOT contained in a MRP secondary report?
(Multiple Choice)
4.8/5
(36)