Exam 6: Process Selection and Facility Layout
Exam 1: Introduction to Operations Management74 Questions
Exam 2: Competitiveness, Strategy, and Productivity72 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design76 Questions
Exam 4: Extension: Reliability12 Questions
Exam 5: Strategic Capacity Planning for Products and Services106 Questions
Exam 5: Extension: Decision Theory123 Questions
Exam 6: Process Selection and Facility Layout150 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 7: Extension: Learning Curves68 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 8: Extension: The Transportation Model20 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 10: Extension: Acceptance Sampling65 Questions
Exam 11: Aggregate Planning and Master Scheduling88 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management161 Questions
Exam 14: Jit and Lean Operations87 Questions
Exam 14: Extension: Maintenance38 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming111 Questions
Select questions type
A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product: Task Time (secs) Immediate Predecessor 3 none 4 none 5 , 7 none 9 , Without regard to projected demand, what is the minimum possible cycle time for this assembly line?
(Multiple Choice)
4.9/5
(33)
Given the following process layout data for locating four departments (A, B, C, and D) in four areas (1, 2, 3, and 4): Distances (meters) Flows (loads per week From/To 1 2 3 4 1 - 50 100 150 2 - 50 100 3 - 50 4 - From/To A B C D A - 10 40 50 B 30 - 10 70 C 60 10 - 40 D 30 50 20 - If departments A through D were to be located in areas 1 through 4, respectively, what would be the total distance loads would be moved each month?
(Short Answer)
5.0/5
(43)
What is it about job shops that make them appropriate for products in the introductory phase of their life cycle?
(Multiple Choice)
4.7/5
(38)
None of the approaches to line balancing, manual or computerized, guarantees an optimal solution.
(True/False)
4.9/5
(43)
Laser technology used in surgical procedures is an example of technological advances in:
(Multiple Choice)
4.9/5
(39)
A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product: Task Time (secs) Immediate Predecessor 3 none 4 none 5 , 7 none 9 , For output to equal projected demand, what should be the actual cycle time for this assembly line?
(Multiple Choice)
4.8/5
(38)
In which type of processing system would gasoline be produced from crude oil?
(Multiple Choice)
4.9/5
(41)
Which of the following is not a primary concern for process selection?
(Multiple Choice)
4.9/5
(32)
A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product: Task Time (secs) Immediate Predecessor 3 none 4 none 5 , 7 none 9 , For output to equal projected demand, what will be the efficiency of the assembly line that uses the minimum number of workstations?
(Multiple Choice)
4.9/5
(38)
QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Task Time (secs) Immediate Predecessor a 34 none b 20 a c 10 b d 16 b e 10 c f 24 d, e g 38 f For output to equal forecasted demand, what will be the second task performed at the second workstation of the production line that uses the fewest number of stations?
(Multiple Choice)
4.8/5
(33)
QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Task Time (secs) Immediate Predecessor a 34 none b 20 a c 10 b d 16 b e 10 c f 24 d, e g 38 f For output to equal forecasted demand, what should be the actual cycle time for this production?
(Multiple Choice)
4.8/5
(39)
The process of assigning tasks to workstations in such a way that the workstations have approximately equal time requirements is called:
(Multiple Choice)
4.9/5
(34)
The key questions in the process selection task are:
(I) How will the product/service be priced?
(II) How much variety will be imposed on the process?
(III) What is the target market for the product/service?
(IV) At what volume will the process need to operate?
(Multiple Choice)
4.8/5
(33)
There are three basic process types: input, processing, and output.
(True/False)
4.8/5
(31)
Which of these items would be most likely to be made with a fixed-position layout?
(Multiple Choice)
4.7/5
(38)
Showing 41 - 60 of 150
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)