Exam 6: Process Selection and Facility Layout
Exam 1: Introduction to Operations Management74 Questions
Exam 2: Competitiveness, Strategy, and Productivity72 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design76 Questions
Exam 4: Extension: Reliability12 Questions
Exam 5: Strategic Capacity Planning for Products and Services106 Questions
Exam 5: Extension: Decision Theory123 Questions
Exam 6: Process Selection and Facility Layout150 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 7: Extension: Learning Curves68 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 8: Extension: The Transportation Model20 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 10: Extension: Acceptance Sampling65 Questions
Exam 11: Aggregate Planning and Master Scheduling88 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management161 Questions
Exam 14: Jit and Lean Operations87 Questions
Exam 14: Extension: Maintenance38 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming111 Questions
Select questions type
Repetitive processing systems usually produce goods specifically for customer orders rather than for inventory.
(True/False)
4.8/5
(44)
Given the following process layout data for locating four departments (A, B, C, and D) in four areas (1, 2, 3, and 4): Distances (meters) Flows (loads per week From/To 1 2 3 4 1 - 50 100 150 2 - 50 100 3 - 50 4 - From/To A B C D A - 10 40 50 B 30 - 10 70 C 60 10 - 40 D 30 50 20 - If transportation costs are $.25 per load per foot moved, what are total monthly costs for an optimum layout?
(Short Answer)
4.9/5
(35)
The main issue in the design of process layouts for service operations concerns the relative positioning of:
(Multiple Choice)
4.8/5
(41)
A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $.50 per load meter moved. An analyst has prepared the following flow and distance matrices: Distances (meters) Flows (loads per week From/To I II III I - 10 20 II - 10 III - From/To - 0 80 30 - 150 100 130 - What is the total flow (loads per week) between department Y and department Z?
(Multiple Choice)
4.9/5
(40)
A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $.50 per load per meter moved. An analyst has prepared the following distances and flow matrices: Distances (meters) Flows (loads per week From/To I II III I - 10 20 II - 10 III - From/To - 60 90 40 - 160 110 140 - What are total weekly costs for the least costly process layout?
(Multiple Choice)
4.8/5
(42)
A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product: Task Time (secs) Immediate Predecessor 3 none 4 none 5 , 7 none 9 , For output to equal projected demand, what is the minimum number of workstations needed?
(Multiple Choice)
4.8/5
(35)
The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved in the production of a Mint Chocolate Chip Cookie. Task Time ( secs ) Immediate Predecessor 4 none 14 12 12 6 8 , For output to equal projected demand, what will be the first task performed at the third workstation of the production line which uses the minimum number of stations?
(Multiple Choice)
4.9/5
(42)
Which closeness rating reflects indifference on the nearness or lack of nearness of two departments?
(Multiple Choice)
4.8/5
(37)
Which type of processing system tends to produce the most product variety?
(Multiple Choice)
4.7/5
(42)
The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved in the production of a Mint Chocolate Chip Cookie. Task Time ( secs ) Immediate Predecessor 4 none 14 12 12 6 8 , For output to equal projected demand, what will be the efficiency of the production line that uses the minimum number of workstations?
(Multiple Choice)
4.9/5
(38)
A service organization (for example, a hospital) is likely to use a(n) ________ layout because of variability in customer processing requirements.
(Multiple Choice)
4.8/5
(41)
The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved in the production of a Mint Chocolate Chip Cookie. Task Time ( secs ) Immediate Predecessor 4 none 14 12 12 6 8 , Without considering projected demands, what is the minimum possible cycle time for this production line?
(Multiple Choice)
4.8/5
(37)
Mismatches between operational capabilities and market demand can have a negative impact on an organization.
(True/False)
4.8/5
(34)
A job-shop processing system generally requires less-skilled workers than a continuous processing system.
(True/False)
5.0/5
(42)
Given the following line balance data: Task Predecessor Time (seconds) none 15 14 7 6 8 , 10 21 For eight hours of operating time per day and a desired output rate of 960 units per day, what is the efficiency for the balance which uses the minimum number of stations?
(Short Answer)
4.8/5
(38)
Product layouts can more easily adapt to variations in product requirements than process layouts can.
(True/False)
4.8/5
(30)
A process layout is more susceptible to shutdowns caused by equipment breakdowns than a product layout.
(True/False)
4.8/5
(34)
The substitution of machinery that has sensing and control devices for human labor is best described by the term:
(Multiple Choice)
4.9/5
(39)
A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are: Task Time (secs) Immediate Predecessor 30 none 30 6 12 54 30 , If the company wants the output rate to be equal to demand, what would be the efficiency of this line with the minimum number of workstations?
(Multiple Choice)
4.8/5
(38)
Service layouts must be visually pleasing as well as functional.
(True/False)
4.8/5
(45)
Showing 101 - 120 of 150
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)