Exam 6: Process Selection and Facility Layout

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

In cellular manufacturing, machines and equipment are grouped by type (e.g., all grinders are grouped into a cell).

(True/False)
4.8/5
(35)

The goal of line balancing is to assign tasks to workstations in such a way that the workstations have approximately equal time requirements.

(True/False)
4.9/5
(41)

Avoiding bottlenecks is the primary goal of product design.

(True/False)
4.9/5
(45)

A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are: Task Time (secs) Immediate Predecessor 30 none 30 6 12 54 30 , If the company wants the output rate to be equal to demand, what is the desired cycle time (in seconds)?

(Multiple Choice)
4.9/5
(36)

A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $.50 per load meter moved. An analyst has prepared the following flow and distance matrices: Distances (meters) Flows (loads per week From/To I II III I - 10 20 II - 10 III - From/To - 0 80 30 - 150 100 130 - What are total weekly costs for an optimum layout?

(Multiple Choice)
4.8/5
(30)

Given the following line balance data: Task Predecessor Time (seconds) none 15 14 7 6 8 , 10 21 For eight hours of operating time per day and a desired output rate of 960 units per day, what is the minimum number of stations needed to achieve the appropriate cycle time?

(Short Answer)
4.9/5
(36)

The type of layout in which workers, materials, and equipment are moved to the product as needed is:

(Multiple Choice)
4.8/5
(30)

QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Task Time (secs) Immediate Predecessor a 34 none b 20 a c 10 b d 16 b e 10 c f 24 d, e g 38 f For output to equal forecasted demand, what is the minimum number of workstations needed?

(Multiple Choice)
4.9/5
(34)

Given the following line balance data: Task Predecessor Time (seconds) none 15 14 7 6 8 , 10 21 What is the maximum possible cycle time?

(Short Answer)
4.8/5
(42)

If a line is balanced with 80 percent efficiency, the "balance delay" will be:

(Multiple Choice)
4.7/5
(36)

Heuristic rules are used primarily in which of these types of layouts? (I) Product (II) Process (III) Fixed-position

(Multiple Choice)
4.8/5
(33)

Which of the following is not true about process layouts when they are compared to product layouts?

(Multiple Choice)
5.0/5
(40)

Which of the following process types would be most likely to be used in the maturity phase of a product's life cycle?

(Multiple Choice)
4.8/5
(37)

Which of the following is not a characteristic of layout decisions in system design?

(Multiple Choice)
4.8/5
(47)

Which of the following is not a process commonly considered in making products or delivering services?

(Multiple Choice)
4.8/5
(37)

Product layouts involve high utilization of labor and equipment.

(True/False)
4.8/5
(38)

As a general rule, continuous processing systems produce products for inventory rather than for customer order.

(True/False)
4.9/5
(41)

A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are: Task Time (secs) Immediate Predecessor 30 none 30 6 12 54 30 , If the company wants the output rate to be equal to demand, what is the minimum number of workstations needed?

(Multiple Choice)
4.9/5
(32)

"Balance delay" is another name for the percentage of idle time in a product layout.

(True/False)
4.9/5
(32)

The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved in the production of a Mint Chocolate Chip Cookie. Task Time ( secs ) Immediate Predecessor 4 none 14 12 12 6 8 , For output to equal projected demand, what is the minimum number of workstations needed?

(Multiple Choice)
4.9/5
(38)
Showing 121 - 140 of 150
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)