Exam 6: Process Selection and Facility Layout
Exam 1: Introduction to Operations Management74 Questions
Exam 2: Competitiveness, Strategy, and Productivity72 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design76 Questions
Exam 4: Extension: Reliability12 Questions
Exam 5: Strategic Capacity Planning for Products and Services106 Questions
Exam 5: Extension: Decision Theory123 Questions
Exam 6: Process Selection and Facility Layout150 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 7: Extension: Learning Curves68 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 8: Extension: The Transportation Model20 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 10: Extension: Acceptance Sampling65 Questions
Exam 11: Aggregate Planning and Master Scheduling88 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management161 Questions
Exam 14: Jit and Lean Operations87 Questions
Exam 14: Extension: Maintenance38 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming111 Questions
Select questions type
In cellular manufacturing, machines and equipment are grouped by type (e.g., all grinders are grouped into a cell).
(True/False)
4.8/5
(35)
The goal of line balancing is to assign tasks to workstations in such a way that the workstations have approximately equal time requirements.
(True/False)
4.9/5
(41)
A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are: Task Time (secs) Immediate Predecessor 30 none 30 6 12 54 30 , If the company wants the output rate to be equal to demand, what is the desired cycle time (in seconds)?
(Multiple Choice)
4.9/5
(36)
A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $.50 per load meter moved. An analyst has prepared the following flow and distance matrices: Distances (meters) Flows (loads per week From/To I II III I - 10 20 II - 10 III - From/To - 0 80 30 - 150 100 130 - What are total weekly costs for an optimum layout?
(Multiple Choice)
4.8/5
(30)
Given the following line balance data: Task Predecessor Time (seconds) none 15 14 7 6 8 , 10 21 For eight hours of operating time per day and a desired output rate of 960 units per day, what is the minimum number of stations needed to achieve the appropriate cycle time?
(Short Answer)
4.9/5
(36)
The type of layout in which workers, materials, and equipment are moved to the product as needed is:
(Multiple Choice)
4.8/5
(30)
QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Task Time (secs) Immediate Predecessor a 34 none b 20 a c 10 b d 16 b e 10 c f 24 d, e g 38 f For output to equal forecasted demand, what is the minimum number of workstations needed?
(Multiple Choice)
4.9/5
(34)
Given the following line balance data: Task Predecessor Time (seconds) none 15 14 7 6 8 , 10 21 What is the maximum possible cycle time?
(Short Answer)
4.8/5
(42)
If a line is balanced with 80 percent efficiency, the "balance delay" will be:
(Multiple Choice)
4.7/5
(36)
Heuristic rules are used primarily in which of these types of layouts?
(I) Product
(II) Process
(III) Fixed-position
(Multiple Choice)
4.8/5
(33)
Which of the following is not true about process layouts when they are compared to product layouts?
(Multiple Choice)
5.0/5
(40)
Which of the following process types would be most likely to be used in the maturity phase of a product's life cycle?
(Multiple Choice)
4.8/5
(37)
Which of the following is not a characteristic of layout decisions in system design?
(Multiple Choice)
4.8/5
(47)
Which of the following is not a process commonly considered in making products or delivering services?
(Multiple Choice)
4.8/5
(37)
Product layouts involve high utilization of labor and equipment.
(True/False)
4.8/5
(38)
As a general rule, continuous processing systems produce products for inventory rather than for customer order.
(True/False)
4.9/5
(41)
A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are: Task Time (secs) Immediate Predecessor 30 none 30 6 12 54 30 , If the company wants the output rate to be equal to demand, what is the minimum number of workstations needed?
(Multiple Choice)
4.9/5
(32)
"Balance delay" is another name for the percentage of idle time in a product layout.
(True/False)
4.9/5
(32)
The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved in the production of a Mint Chocolate Chip Cookie. Task Time ( secs ) Immediate Predecessor 4 none 14 12 12 6 8 , For output to equal projected demand, what is the minimum number of workstations needed?
(Multiple Choice)
4.9/5
(38)
Showing 121 - 140 of 150
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)