Some of the advantages of a functional project where the project is housed in a functional division include which of the following?

Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
Verified

C

Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs. Immediate Normal Crash Normal Crash Activity Predecessor Time Time Cost Cost A None 3 2 \ 200 \ 400 B A 4 3 \ 300 \ 600 C A 1 1 \ 200 \ 200 D B and C 3 2 \ 500 \ 550 E D 2 1 \ 500 \ 900 What are the total time of this project and total normal cost?

Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
Verified

B

What is that sequence of activities that consume the longest amount of time in a project network of activities called? _______________________________

Free
(Short Answer)
4.8/5
(40)
Correct Answer:
Verified

The critical path
Explanation: The critical path of activities in a project is the sequence of activities that form the longest chain in terms of their time to complete

What is the most basic requirement of an EVM system? _____________________________________________________________

(Short Answer)
4.9/5
(36)

A simple project listing of five activities and their respective time estimates are presented below: Activity Immediate Predecessor Time in Days A None 1 B A 2 C A 1 D B and C 3 E D 2 Using CPM,which activities make up the critical path?

(Multiple Choice)
4.8/5
(35)

A project may be defined as a series of related jobs directed toward some major output and requiring a significant period of time to perform.

(True/False)
4.8/5
(37)

Slack activity time is the difference between the early start and the late finish of a project activity time.

(True/False)
4.9/5
(32)

What do the initials EVM stand for? _______________________________________

(Short Answer)
4.9/5
(34)

You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values.What can you conclude?

(Multiple Choice)
4.9/5
(38)

The activity direct costs associated with a project might include giving workers overtime to complete a project in less-than the expected time.

(True/False)
4.9/5
(31)

A project starts out as which of the following?

(Multiple Choice)
4.8/5
(39)

In a CPM analysis if you subtract the early start from the late start the result is the activity's slack time.

(True/False)
4.8/5
(32)

CPM is an abbreviation for Critical Path Method.

(True/False)
4.7/5
(33)

Earned Value Management (EVM)has the capability to combine measurements of scope,schedule and cost in a project.

(True/False)
4.8/5
(33)

The Gantt chart is an example of a project control chart.

(True/False)
4.9/5
(27)

The critical path of activities in a project is the sequence of activities that form the shortest chain in a project network of activities.

(True/False)
4.8/5
(30)

A matrix project structure is often referred to as a "skunkworks."

(True/False)
4.9/5
(42)

In the Time-Cost CPM model,cost is assumed to be a linear function of time.

(True/False)
4.7/5
(45)

A disadvantage of a matrix project organizational structure is that a project manager is held responsible for successful completion of the project.

(True/False)
4.8/5
(28)

A project milestone is a specific event to be reached by a particular point in time.

(True/False)