Exam 5: Projects
Exam 1: Operations and Supply Chain Management84 Questions
Exam 2: Strategy and Sustainability54 Questions
Exam 3: Forecasting101 Questions
Exam 4: Strategic Capacity Management64 Questions
Exam 5: Projects77 Questions
Exam 6: Manufacturing and Service Processes73 Questions
Exam 7: Service Processes85 Questions
Exam 8: Sales and Operations Planning65 Questions
Exam 9: Material Requirements Planning89 Questions
Exam 10: Quality Management and Six Sigma149 Questions
Exam 11: Inventory Management108 Questions
Exam 12: Lean Supply Chains73 Questions
Exam 13: Global Sourcing and Procurement78 Questions
Exam 14: Location, Logistics, and Distribution61 Questions
Select questions type
Some of the advantages of a functional project where the project is housed in a functional division include which of the following?
Free
(Multiple Choice)
4.9/5
(36)
Correct Answer:
C
Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs. Immediate Normal Crash Normal Crash Activity Predecessor Time Time Cost Cost A None 3 2 \ 200 \ 400 B A 4 3 \ 300 \ 600 C A 1 1 \ 200 \ 200 D B and C 3 2 \ 500 \ 550 E D 2 1 \ 500 \ 900
What are the total time of this project and total normal cost?
Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
B
What is that sequence of activities that consume the longest amount of time in a project network of activities called? _______________________________
Free
(Short Answer)
4.8/5
(40)
Correct Answer:
The critical path
Explanation: The critical path of activities in a project is the sequence of activities that form the longest chain in terms of their time to complete
What is the most basic requirement of an EVM system? _____________________________________________________________
(Short Answer)
4.9/5
(36)
A simple project listing of five activities and their respective time estimates are presented below: Activity Immediate Predecessor Time in Days A None 1 B A 2 C A 1 D B and C 3 E D 2
Using CPM,which activities make up the critical path?
(Multiple Choice)
4.8/5
(35)
A project may be defined as a series of related jobs directed toward some major output and requiring a significant period of time to perform.
(True/False)
4.8/5
(37)
Slack activity time is the difference between the early start and the late finish of a project activity time.
(True/False)
4.9/5
(32)
What do the initials EVM stand for? _______________________________________
(Short Answer)
4.9/5
(34)
You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values.What can you conclude?
(Multiple Choice)
4.9/5
(38)
The activity direct costs associated with a project might include giving workers overtime to complete a project in less-than the expected time.
(True/False)
4.9/5
(31)
In a CPM analysis if you subtract the early start from the late start the result is the activity's slack time.
(True/False)
4.8/5
(32)
Earned Value Management (EVM)has the capability to combine measurements of scope,schedule and cost in a project.
(True/False)
4.8/5
(33)
The critical path of activities in a project is the sequence of activities that form the shortest chain in a project network of activities.
(True/False)
4.8/5
(30)
A matrix project structure is often referred to as a "skunkworks."
(True/False)
4.9/5
(42)
In the Time-Cost CPM model,cost is assumed to be a linear function of time.
(True/False)
4.7/5
(45)
A disadvantage of a matrix project organizational structure is that a project manager is held responsible for successful completion of the project.
(True/False)
4.8/5
(28)
A project milestone is a specific event to be reached by a particular point in time.
(True/False)
4.7/5
(30)
Showing 1 - 20 of 77