Exam 18: Introduction to Systems Development and Systems Analysis
Exam 1: Accounting Information Systems83 Questions
Exam 2: Overview of Business Processes105 Questions
Exam 3: Systems Development and Documentation Techniques99 Questions
Exam 4: Relational Databases90 Questions
Exam 5: Computer Fraud and Security95 Questions
Exam 6: Control and Accounting Information Systems87 Questions
Exam 7: Infromation System Controls for Systems Reliability82 Questions
Exam 8: Auditing Computer-Based Information Systems77 Questions
Exam 9: Auditing Computer-Based Informtion Systems94 Questions
Exam 10: The Revenue Cycle: Sales an Cash Collections94 Questions
Exam 11: The Expenditure Cycle: Purchasing and Cash Disbursements89 Questions
Exam 12: The Production Cycle87 Questions
Exam 13: The Human Resources Managementpayroll Cycle93 Questions
Exam 14: General Ledger and Reporting System81 Questions
Exam 15: Data Modeling and Database Design80 Questions
Exam 16: Implementing an Rea Model in a Relational Database77 Questions
Exam 17: Special Topics in Rea Modeling77 Questions
Exam 18: Introduction to Systems Development and Systems Analysis94 Questions
Exam 19: Ais Development Strategies95 Questions
Exam 20: Systems Design, Implementation and Operation86 Questions
Select questions type
A network of arrows and nodes representing project activities that require an expenditure of time and resources and the completion of initiation of activities,respectively,is called
(Multiple Choice)
4.9/5
(37)
__________ requires that all activities and the precedent and subsequent relationships among them be identified.
(Multiple Choice)
4.8/5
(35)
When the information is brief and well defined,which is the best data-gathering approach to use?
(Multiple Choice)
4.8/5
(31)
A project development team at Midwest Construction was assigned the task of improving the efficiency of the firm's accounting information system.As part of the ______ step in systems development life cycle,the team has determined that the objectives of the project can be accomplished by installing a new computer system or by upgrading the existing system.
(Multiple Choice)
4.8/5
(41)
One step in the systems development life cycle (SDLC)identifies and evaluates design alternatives and to develop design specifications.This step is called
(Multiple Choice)
4.9/5
(36)
What is the correct sequence of the phases in the systems development life cycle?
(Multiple Choice)
4.8/5
(29)
Continuing to use a manual system instead of the new AIS is a form of resistance known as
(Multiple Choice)
4.7/5
(44)
Which planning technique does not show the relationships among various activities?
(Multiple Choice)
4.7/5
(38)
When using the payback method to determine economic feasibility of projects,the company usually accepts the project with the
(Multiple Choice)
4.9/5
(30)
Refer to the PERT diagram below,where the numbers next to the arrows refer to the number of days required for completion of the corresponding activity.What is the critical path? 

(Multiple Choice)
4.8/5
(26)
Which is the best data-gathering approach to use when information must be obtained from many different people?
(Multiple Choice)
4.8/5
(35)
To minimize adverse behavioral reactions,the organization must first understand why resistance to change occurs.One behavioral problem occurs when there is insufficient explanation of why a change must take place.This type of problem falls into the general category of
(Multiple Choice)
4.8/5
(32)
A federal law demands that certain information about foreign customers should be maintained in the information system.In which part of a feasibility study should this requirement be considered?
(Multiple Choice)
4.9/5
(39)
Refer to the table below,which shows the results of payback,net present value,and internal rate of return analysis of four projects.Which is preferred by the payback criterion? 

(Multiple Choice)
4.9/5
(39)
The question of economic feasibility is important when designing and implementing a new system.Accountants can contribute to feasibility study analysis by evaluating cost savings and other benefits versus operating costs and other cash outflows.This is better known as
(Multiple Choice)
4.7/5
(27)
What is most difficult item to quantify when assessing economic feasibility?
(Multiple Choice)
4.9/5
(40)
An antiquated information system used by an office supply manufacturer caused customer dissatisfaction since it took two days to process a telephone order.After the system was upgraded and redesigned,the time to process a telephone order was reduced to three minutes.This is a prime example of
(Multiple Choice)
4.9/5
(39)
Which of the following aspect of a feasibility study is concerned with meeting external reporting requirements?
(Multiple Choice)
4.9/5
(37)
Which method of data gathering is most likely to result in information that represents the personal biases and opinions of the person giving the information?
(Multiple Choice)
4.9/5
(34)
A project development team at Midwest Construction was assigned the task of improving the efficiency of the firm's accounting information system.As part of the ______ step in systems development life cycle,the team has initiated an end user training program in preparation for switching over to the new system.
(Multiple Choice)
4.9/5
(31)