    Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 3,5,and
Solved

Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 3,5,and

Question 68

Question 68

Multiple Choice

Given an activity's optimistic,most likely,and pessimistic time estimates of 3,5,and 15 days,respectively,compute the PERT standard deviation for this activity.


A) 2
B) 4
C) 5
D) 15
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q63: Slack is the time an activity can

Q64: Which of the following is not a

Q65: Table 11-5 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-5

Q67: Table 11-6 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-6

Q71: In PERT,the variance in completion time is

Q72: Which of the following statements about project

Q73: Given an activity's optimistic,most likely,and pessimistic time

Q105: PERT and CPM are quantitative analysis tools

Q114: One PERT/COST assumption is that money is

Q137: Activity C of a project has a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines