Multiple Choice
The table below shows PERT estimates te) for activities A through E.
Based on the table above, the te) for activities A, B and C are: .
A) 5 days, 3 days, 6 days
B) 5.500 days, 3.333 days, 6.167 days
C) 6 days, 3.667 days, 6.333 days
D) 3.167 days, 5.333 days, 1.833 days
E) 3 days, 1.667 days, 1.833 days
F) None of the above
Correct Answer:

Verified
Correct Answer:
Verified