Multiple Choice
The following network shows a portion of an IT project involving programming, hardware installation, and implementation. As shown, programming and hardware installation are both estimated to be 52 days in duration. These estimates are not exact, given the uncertainty that can occur in any project environment, but they do share the same statistical distribution, with 52 as the median value.
Given what is covered in Chapter 6 regarding two tasks that merge into a common successor, what is the approximate probability that implementation can begin at the end of 52 days of concurrent work on programming and hardware installation?
A) 0%
B) 25%
C) 50%
D) 75%
E) 100%
Correct Answer:

Verified
Correct Answer:
Verified
Q11: The following software development plan is the
Q12: The following information is the basis
Q13: Activity time estimates for the following project
Q14: Which of the following schedule display formats
Q15: The following network is the basis for
Q17: The following network is the basis for
Q18: The following network is the basis for
Q19: The following information is the basis
Q20: The table below shows PERT estimates
Q21: The following software development plan is the