Multiple Choice
The following network is the basis for the next four questions:
-Assume all activities are scheduled to begin on their early start times. How much free float slack) does activity B have?
A) 0 days
B) 1 day
C) 2 days
D) 3 days
E) 4 days
F) 5 days
Correct Answer:

Verified
Correct Answer:
Verified