Solved

The Following Network Is the Basis for the Next Four

Question 17

Multiple Choice

The following network is the basis for the next four questions:
The following network is the basis for the next four questions:     -Assume all activities are scheduled to begin on their early start times. How much free float slack)  does activity B have?  A)  0 days B)  1 day C)  2 days D)  3 days E)  4 days F)  5 days

-Assume all activities are scheduled to begin on their early start times. How much free float slack) does activity B have?


A) 0 days
B) 1 day
C) 2 days
D) 3 days
E) 4 days
F) 5 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions