Solved

The Next Three Questions Are Related to the Project Schedule

Question 12

Multiple Choice

The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.     -Given the way the schedule shown above is currently planned, what sequence of activities comprises the critical chain? Dashed lines = float.)   A)  A-B-C-F-H-J B)  A-B-D-J C)  A-B-D-G-I-J D)  A-B-C-G-I-J E)  ABEGIJ F)  A-E-J

-Given the way the schedule shown above is currently planned, what sequence of activities comprises the critical chain? Dashed lines = float.)


A) A-B-C-F-H-J
B) A-B-D-J
C) A-B-D-G-I-J
D) A-B-C-G-I-J
E) ABEGIJ
F) A-E-J

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions