Multiple Choice
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
-Given the way the schedule shown above is currently planned, what sequence of activities comprises the critical chain? Dashed lines = float.)
A) A-B-C-F-H-J
B) A-B-D-J
C) A-B-D-G-I-J
D) A-B-C-G-I-J
E) ABEGIJ
F) A-E-J
Correct Answer:

Verified
Correct Answer:
Verified