Multiple Choice
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
-In the network shown above, where would a resource buffer be most appropriate from among the options below?
A) Between H and J
B) Between A and C
C) Between B and C
D) Between C and F
E) Between D and J
Correct Answer:

Verified
Correct Answer:
Verified