Multiple Choice
The next three questions relate to the following scenario: Erica is planning a large surprise party for her best friend. She has developed the plan below which includes estimates of the time in hours) and cost necessary to perform each of the activities required.
-Based on critical chain concepts, which of the following is true of a resource buffer?
A) A resource buffer involves information sharing between sequentially-linked tasks on the critical chain.
B) A resource buffer collects time at the end of the project.
C) A resource buffer specifies a minimum amount of free float to protect the critical chain from the effects of potential delays in non-critical chain activities.
D) A resource buffer adds extra human or financial resources to the critical chain to account for potential uncertainties in task times.
E) A and B only.
Correct Answer:

Verified
Correct Answer:
Verified
Q6: Using the following figures, what is the
Q7: The next three questions relate to
Q8: When is crashing beneficial to a project?
Q9: Which of the following is most associated
Q10: The next three questions are related to
Q12: The next three questions are related to
Q13: In critical chain terminology, removing some of
Q14: Which of the following would NOT be
Q15: Fast tracking is defined as: <br>A) adding
Q16: The next three questions are related to