Multiple Choice
Which of the following is most associated with fast tracking?
A) A waterfall-type schedule
B) Project activities are delayed to accommodate resource conflicts
C) Finish-to-start precedence logic
D) Start-to-start precedence logic
E) Paying incentives for faster work
Correct Answer: