Multiple Choice
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
-In the network shown above, given the current placement of float, where would a feeding buffer be most appropriate from among the options below?
A) Between A and B
B) Between D and J
C) Between E and G
D) Between F and H
E) Between E and I
Correct Answer:

Verified
Correct Answer:
Verified