Multiple Choice
In critical chain terminology, removing some of the time buffer from individual activity estimates and moving them collectively to the end of the project is an example of:
A) Inserting a project buffer
B) Inserting a feeding buffer
C) Inserting a resource buffer
D) Inserting float
E) Inserting a critical path
Correct Answer:

Verified
Correct Answer:
Verified