Multiple Choice
When is crashing beneficial to a project?
A) When the cost of crashing by one day is less than the project's daily overhead cost
B) When the cost of crashing by one day is more than the project's daily overhead cost.
C) When there are no delay penalties
D) When the task to be crashed is not on the critical path
E) A and C