Multiple Choice
Which is the CORRECT approach for managing a large improvement initiative as smaller iterations?
A) Each iteration should be designed before starting the initiative and implemented without feedback
B) Feedback should only be taken into account when one iteration fails to meet its objective
C) Feedback should be reduced for large improvements as it is unlikely that circumstances will change
D) Each iteration should be continually re-evaluated based on feedback
Correct Answer:

Verified
Correct Answer:
Verified
Q30: Which activity is part of the 'continual
Q31: Which practice uses technologies such as intelligent
Q32: Which statement about value creating activities is
Q33: What is a service?<br>A) A possible event
Q34: Which guiding principle recommends using the minimum
Q36: Which practice recommends using tools for collaboration
Q37: Which is an example of a business
Q38: What is the definition of a known
Q39: Which two statements about the guiding principles
Q40: Which competencies are required by the 'service