Multiple Choice
Which statement is incorrect:
A) Unlike the critical path, the critical chain ensures stability on the project.
B) The critical chain is likely to reduce project duration.
C) The critical chain is, in general, longer than the critical path.
D) The critical chain results in a high probability of finishing the project on the promised date.
E) Unlike the critical path, the critical chain ensures that a resource is scheduled to do only one activity at any specific time.
Correct Answer:

Verified
Correct Answer:
Verified
Q19: Statement: A "resource loading" chart shows the
Q20: Which statement is correct: In the CPM,
Q21: Statement: In PERT, the mean (expected) time
Q22: Contingencies should be built in at the
Q23: If the project completion has a distribution
Q24: A project cannot have more than one
Q25: The Following Questions adapted from tutorial
Q26: When there are multiple critical paths and
Q28: The following buffer enables the project manager
Q29: Statement: In resource loading, the project schedule