The following buffer enables the project manager to focus on critical activities by ensuring that the critical chain does not change during project execution:
A) Milestone
B) Feeding
C) Project
D) Resource
E) The combination of (b) and (d) above
Correct Answer:

Verified
Correct Answer:
Verified