If the most optimistic time for completing an activity is 14,the most likely time is 16,and the most pessimistic time is 30,then the estimated time for the activity is ______.
A) 18
B) 19
C) 20
D) 21
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q61: If a project has an expected completion
Q62: Planned value is _.<br>A)the total budget<br>B)a way
Q63: The cost of the project is given
Q64: The probability that a project will be
Q65: An activity was given a planned budget
Q67: If a project is expected to be
Q68: If the most optimistic time for completing
Q69: If a project is expected to be
Q70: Which of the following statements is FALSE
Q71: If the standard deviation is 3.5,the Z