Multiple Choice
The probability that a project will be completed within a specified period of time can be calculated using the standard normal equation,which is ______.
A) (due date - expected date of completion) / the project's standard deviation
B) (expected date of completion - due date) / the project's standard deviation
C) the project's standard deviation / (due date - expected date of completion)
D) the project's standard deviation / (expected date of completion - due date)
Correct Answer:

Verified
Correct Answer:
Verified