Exam 9: Closing the Project
Exam 1: Project Management Concepts99 Questions
Exam 2: Identifying and Selecting Projects92 Questions
Exam 3: Developing Project Proposals153 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence166 Questions
Exam 5: Developing the Schedule127 Questions
Exam 6: Resource Utilization45 Questions
Exam 7: Determining Costs, Budget and Earned Value103 Questions
Exam 8: Managing Risk72 Questions
Exam 9: Closing the Project64 Questions
Exam 10: The Project Manager165 Questions
Exam 11: The Project Team275 Questions
Exam 12: Project Communication and Documentation164 Questions
Exam 13: Project Management Organizational Structures109 Questions
Select questions type
During project closing, the project team or contractor should ensure that copies of appropriate project documentation are properly organized, filed, and archived so that
(Multiple Choice)
4.7/5
(40)
Projects can be terminated by the sponsor or customer due to dissatisfaction with the project progress.
(True/False)
4.7/5
(32)
During the post-project meeting with the customer, which of the follow results is the best outcome to occur?
(Multiple Choice)
5.0/5
(36)
Which of the following would not be a closing action for a project?
(Multiple Choice)
4.8/5
(30)
The project manager should prepare a written performance evaluation of each member of the project team that mentions how each has
(Multiple Choice)
4.8/5
(33)
At the ____ meeting with the project team at the end of the project, the project manager should lead a discussion of what happened during performance of the project and solicit specific recommendations for improvement.
(Multiple Choice)
4.8/5
(44)
Which of the following is the least effective method of evaluating the project's performance?
(Multiple Choice)
4.9/5
(32)
The type of questions the project manager should when meeting with the project sponsor is
(Multiple Choice)
4.9/5
(41)
At the close of the project, the project manager should meet with each project team member individually to
(Multiple Choice)
4.8/5
(30)
The post-project evaluation meeting with the project sponsor should focus on additional projects and assume permission to use the customer as a reference with potential customers.
(True/False)
4.8/5
(37)
The project manager should schedule a post-project meeting with the customer to discuss all of the following except
(Multiple Choice)
4.9/5
(28)
The purpose of identifying and documenting lessons learned is to
(Multiple Choice)
4.8/5
(40)
The purposes of a ____ should be to determine whether the project provided the customer with the anticipated benefits to assess the level of customer satisfaction, and to obtain any feedback that would be helpful in future business relationships with this or other customers.
(Multiple Choice)
4.7/5
(37)
Projects should be terminated by the sponsor or customer due to an increase in the project return on investment .
(True/False)
4.9/5
(42)
The project team should wait until the end of the project to capture and document lessons learned.
(True/False)
4.8/5
(46)
The process of closing the project involves various actions, including
(Multiple Choice)
4.9/5
(33)
What type of knowledge base system should be established by the project organization?
(Essay)
4.7/5
(36)
The ____ should prepare a written report of project performance including lessons learned and recommendations.
(Multiple Choice)
4.8/5
(33)
The project manager should schedule the meeting immediately following the delivery of the final report rather than waiting for a time when the customer is in a position to really determine whether the project met expectations and achieved the anticipated benefits.
(True/False)
4.8/5
(34)
Showing 21 - 40 of 64
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)