Exam 14: Project Closeout and Termination

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

The final items that are left to accomplish or correct at the end of a construction project are on the:

(Multiple Choice)
4.8/5
(29)

The formalized system of dealing with grievances and administering corrective justice to parties in a bargaining position is:

(Multiple Choice)
4.7/5
(34)

An internal intellectual issue that arises when a project is terminated is:

(Multiple Choice)
4.8/5
(37)

The disadvantage of a BOOT contract to the project organization is that they must take on:

(Multiple Choice)
4.9/5
(40)

Business benefits are often crucial; so many projects must first clear __________ as a criterion for their selection and startup.

(Short Answer)
4.9/5
(38)

Termination by addition and termination by integration both represent successful project completion.

(True/False)
4.9/5
(35)

Research clearly demonstrates that when team members have experienced positive psycho-social outcomes from a project they are __________ to work collaboratively in the future.

(Short Answer)
4.7/5
(36)

Which type of project termination can occur for a project that is successful and for a project that is unsuccessful?

(Multiple Choice)
4.8/5
(33)

The project review session was one epiphany after another for the project organization. A number of systematic errors were properly identified and the root causes of a number of problems were identified. Sadly, the review session was not leveraged to its fullest extent thanks to:

(Multiple Choice)
4.8/5
(40)

__________ can be made by a client when there is not a contractual basis for a lawsuit but they consider that because of some unexpected event there is a moral or commercial obligation on the project organization to pay compensation.

(Short Answer)
4.9/5
(34)

Which statement about project closeout activities is best?

(Multiple Choice)
4.7/5
(43)

Researchers have determined that one significant early warning sign of project failure is:

(Multiple Choice)
4.8/5
(46)

The work breakdown for project termination issues can be broadly categorized into:

(Multiple Choice)
4.9/5
(40)

A mainframe computer company decided to enter the personal computer market with its Floridian Project, but subsequently decided to leave the market to focus on the mainframe business. The decision rule that they probably applied was to get out:

(Multiple Choice)
4.8/5
(34)

The actual carryover from one project to another is minimal because projects are unique, one-time events.

(True/False)
4.8/5
(41)

Describe and rank any three decision rules for terminating an ongoing project before completion.

(Essay)
4.9/5
(44)

The closeout step that requires all contractual documents be recorded and archived is:

(Multiple Choice)
4.7/5
(41)

What are the major types of paperwork that must be closed out at the end of a project? What are some elements of each type?

(Essay)
4.9/5
(32)

Which of these is NOT a consequence of a natural process for project closeout?

(Multiple Choice)
4.9/5
(43)

Which of these statements about early termination decisions is best?

(Multiple Choice)
4.9/5
(32)
Showing 21 - 40 of 100
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)