Exam 14: Project Closeout and Termination
Exam 1: Introduction: Why Project Management88 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture90 Questions
Exam 3: Project Selection and Portfolio Management95 Questions
Exam 4: Leadership and the Project Manager108 Questions
Exam 5: Scope Management96 Questions
Exam 6: Project Team Building, Conflict, and Negotiation104 Questions
Exam 7: Risk Management95 Questions
Exam 8: Cost Estimation and Budgeting95 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path98 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks90 Questions
Exam 11: Critical Chain Project Scheduling98 Questions
Exam 12: Resource Management79 Questions
Exam 13: Project Evaluation and Control98 Questions
Exam 14: Project Closeout and Termination100 Questions
Select questions type
What are any four items that prevent effective project closeouts and how can each be avoided?
(Essay)
4.9/5
(39)
A comparison of matrix versus functional design would fall under the:
(Multiple Choice)
4.9/5
(40)
The difference between a BOT contract and a BOOT contract is that under the BOOT contract:
(Multiple Choice)
4.8/5
(37)
The build, operate, transfer option for projects requires the project contractor to take initial ownership of the project in order to make sure it works, thus mitigating risk in the short run.
(True/False)
4.9/5
(43)
Research indicates that the number one reason for terminating research and development projects is:
(Multiple Choice)
4.9/5
(33)
Some of the greatest challenges facing project teams during termination is:
(Multiple Choice)
4.8/5
(42)
When contractual claims are defaulted due to the failure of a project to be completed and delivered:
(Multiple Choice)
4.8/5
(35)
Loss of team identify during project termination is a significant internal intellectual issue.
(True/False)
4.9/5
(33)
Which of the following is NOT a component of a baseline project assessment system?
(Multiple Choice)
4.8/5
(36)
A lessons-learned analysis falls under the project closeout management element of:
(Multiple Choice)
4.9/5
(40)
What are the two types of claims that can arise in the event of project closure and why would one be chosen over another?
(Essay)
4.8/5
(39)
Arbitration refers to the formalized system for dealing with grievances and administering corrective justice to parties in a bargaining situation.
(True/False)
4.9/5
(36)
Activity and funding for the CEO's pet project stopped during the economic downturn and even after her retirement the file remained open. A few years and 30% turnover later, many employees didn't know the purpose of the half finished obelisk in the cafeteria. The obelisk was fated to a permanent half-finished state thanks to its termination by __________.
(Short Answer)
4.9/5
(43)
A final report section on the techniques of project management would include an honest assessment of whether the:
(Multiple Choice)
4.8/5
(41)
Static factors that may play a role in the decision to terminate a project early include company image and the presence of high sunk costs.
(True/False)
4.9/5
(44)
What is arbitration, how does it work, when is it used and what are the two different types?
(Essay)
4.8/5
(41)
Showing 61 - 80 of 100
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)