Exam 13: Project Evaluation and Control
Exam 1: Introduction: Why Project Management88 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture90 Questions
Exam 3: Project Selection and Portfolio Management95 Questions
Exam 4: Leadership and the Project Manager108 Questions
Exam 5: Scope Management96 Questions
Exam 6: Project Team Building, Conflict, and Negotiation104 Questions
Exam 7: Risk Management95 Questions
Exam 8: Cost Estimation and Budgeting95 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path98 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks90 Questions
Exam 11: Critical Chain Project Scheduling98 Questions
Exam 12: Resource Management79 Questions
Exam 13: Project Evaluation and Control98 Questions
Exam 14: Project Closeout and Termination100 Questions
Select questions type
A recurring problem with establishing accurate or meaningful EVM results has to do with:
Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
C
An excellent way to coordinate schedules with vendors and suppliers is through the use of:
Free
(Multiple Choice)
4.9/5
(35)
Correct Answer:
A
Use the data to calculate the schedule performance index for the project for the end of week 10. All amounts are in thousands of dollars. 

(Multiple Choice)
4.9/5
(39)
In the formation stage, failed projects are more likely to have:
(Multiple Choice)
4.8/5
(36)
The earned value of a project is the cumulative total costs incurred in accomplishing the various work packages.
(True/False)
4.8/5
(34)
The Project Implementation Profile allows teams to make mid-course correction and improvement of the __________.
(Short Answer)
4.8/5
(45)
Briefly describe any seven critical success factors for project success contained in the Project Implementation Profile.
(Essay)
4.9/5
(37)
The degree to which anyone who will be ultimately making use of the product of the project is personally involved in the implementation process is the __________ critical success factor in the Project Implementation Profile.
(Short Answer)
4.9/5
(34)
Use the earned value table for Project Terrace to calculate their schedule performance index if all dollar amounts are in hundreds. 

(Multiple Choice)
4.8/5
(29)
If an activity's progress is defined as 0% until the moment is complete, the project manager is using:
(Multiple Choice)
4.9/5
(31)
A project manager can calculate the projected budget to completion by using the:
(Multiple Choice)
4.7/5
(36)
Use the S-curves for this project to create a table showing budgeted and actual expenses and variance in thousands of dollars and comment on the project's performance. The horizontal axis is in weeks. 

(Essay)
4.8/5
(40)
Measurement mechanisms should include a clear definition of:
(Multiple Choice)
4.7/5
(37)
Use the earned value table for Project Terrace to calculate their estimated time to completion (all dollar amounts are in hundreds). 

(Multiple Choice)
4.7/5
(34)
Take the factors considered by earned value analysis and subtract those considered by tracking Gantt charts. The factor(s) you have remaining are:
(Multiple Choice)
5.0/5
(35)
The project control process is captured in the critical success factor of:
(Multiple Choice)
4.7/5
(40)
Your organization is in the midst of a project in uncharted waters; nothing you have attempted before comes close to many of the activities that are necessary to bring this project to completion. Your earned value management should probably be tracked closely with a percentage complete rule in increments of 5 to 10 percent.
(True/False)
4.7/5
(35)
What is earned value management and how can it be used to monitor project status?
(Essay)
4.8/5
(31)
Showing 1 - 20 of 98
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)