Exam 13: Project Evaluation and Control
Exam 1: Introduction: Why Project Management88 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture90 Questions
Exam 3: Project Selection and Portfolio Management95 Questions
Exam 4: Leadership and the Project Manager108 Questions
Exam 5: Scope Management96 Questions
Exam 6: Project Team Building, Conflict, and Negotiation104 Questions
Exam 7: Risk Management95 Questions
Exam 8: Cost Estimation and Budgeting95 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path98 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks90 Questions
Exam 11: Critical Chain Project Scheduling98 Questions
Exam 12: Resource Management79 Questions
Exam 13: Project Evaluation and Control98 Questions
Exam 14: Project Closeout and Termination100 Questions
Select questions type
One of these things is NOT like the others (that happen to directly predict project success). The one that's different is:
(Multiple Choice)
4.8/5
(33)
Identify a different key success driver and inhibitor for the project stages of formation, build-up, main phase, and close-out.
(Essay)
4.9/5
(46)
Use the earned value table for Project Terrace to determine the earned value (all dollar amounts are in hundreds). 

(Multiple Choice)
4.8/5
(41)
Positive variance on an S-curve represents significant project progress.
(True/False)
4.7/5
(37)
What is a tracking Gantt chart and what are the benefits and drawbacks of its use?
(Essay)
4.8/5
(40)
Project Terrace has an actual cost of $3,000, but their earned value (all dollar amounts are in hundreds) table appears below. What is their cost variance? 

(Multiple Choice)
4.9/5
(39)
The classic S-curve is a plot of cumulative cost versus elapsed time in weeks.
(True/False)
4.7/5
(35)
Gap analysis refers to any measurement process that first determines the goals and then the degree to which the actual performance lives up to those goals.
(True/False)
4.8/5
(36)
What are any four benefits to using milestones as a form of project control? What advantage do they hold over pure S-curve analysis?
(Essay)
4.9/5
(32)
Can earned value be used to manage a portfolio of projects? If so, how would this analysis proceed?
(Essay)
4.7/5
(35)
The schedule performance index is the ratio of the actual cost to the earned value.
(True/False)
4.8/5
(33)
It is possible to measure both positive and negative deviations from the schedule baseline with the tracking Gantt chart.
(True/False)
4.7/5
(32)
Geoff coolly surveyed his earned value table at the conclusion of month 24. It was hard to believe that two short years ago, with his membership at Match.com about to expire, he had managed to craft an ad that was both urbane and manly enough as to catch the eye of the divine Miss Smylie. (The male model photo he substituted for his own certainly didn't hurt either.) Now he was almost done managing this critical project. Some might think him crass for taking such an approach, but he practiced what he preached at the small commuter school where he taught. Calculate all of the schedule and cost variances (costs in the table are in dollars) for this project and comment on Geoff's skills as a project manager.


(Essay)
4.8/5
(30)
Once an activity is begun, it is assumed to be half done under the:
(Multiple Choice)
4.9/5
(40)
Showing 41 - 60 of 98
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)