Exam 13: Project Evaluation and Control

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

A tracking Gantt chart does NOT allow for:

(Multiple Choice)
4.8/5
(38)

What are the inputs and the steps in applying earned value management as a project management tool?

(Essay)
4.8/5
(42)

The project baseline is established by combining data from the:

(Multiple Choice)
4.8/5
(39)

The Project Implementation Profile does NOT contain this critical success factor.

(Multiple Choice)
4.7/5
(48)

At the end of week 20, this project has cost $79,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars. At the end of week 20, this project has cost $79,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars.

(Multiple Choice)
4.8/5
(44)

Project goal setting includes setting a baseline plan, which is predicated on:

(Multiple Choice)
4.7/5
(36)

In the build-up stage of a successful project, it is important that:

(Multiple Choice)
4.8/5
(46)

The earned value to date divided by the planned value of work scheduled to be performed is the:

(Multiple Choice)
4.8/5
(37)

Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks. Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks.

(Multiple Choice)
4.9/5
(35)

The project costs plotted against the elapsed time in weeks is known as the __________.

(Short Answer)
4.7/5
(33)

The one factor that earned value management considers that an S-curve does not include is performance.

(True/False)
4.9/5
(38)

Earned value management jointly considers the impact of:

(Multiple Choice)
4.8/5
(36)

If significant deviations from the project plan are detected, corrective action is taken and then:

(Multiple Choice)
4.9/5
(37)

Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. Use the data to calculate the earned value for the project. All amounts are in thousands of dollars.

(Multiple Choice)
4.9/5
(34)

If the actual cost line on an S-curve undercuts the budgeted cost line, the project has a(n) __________ variance.

(Short Answer)
4.8/5
(37)

The Project Implementation Profile includes this critical success factor.

(Multiple Choice)
4.7/5
(40)

It is possible to measure:

(Multiple Choice)
4.9/5
(37)

In earned value management analysis, the cumulative amount of the budget becomes the:

(Multiple Choice)
4.9/5
(40)
Showing 81 - 98 of 98
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)