Exam 13: Project Evaluation and Control
Exam 1: Introduction: Why Project Management88 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture90 Questions
Exam 3: Project Selection and Portfolio Management95 Questions
Exam 4: Leadership and the Project Manager108 Questions
Exam 5: Scope Management96 Questions
Exam 6: Project Team Building, Conflict, and Negotiation104 Questions
Exam 7: Risk Management95 Questions
Exam 8: Cost Estimation and Budgeting95 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path98 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks90 Questions
Exam 11: Critical Chain Project Scheduling98 Questions
Exam 12: Resource Management79 Questions
Exam 13: Project Evaluation and Control98 Questions
Exam 14: Project Closeout and Termination100 Questions
Select questions type
What are the inputs and the steps in applying earned value management as a project management tool?
(Essay)
4.8/5
(42)
The project baseline is established by combining data from the:
(Multiple Choice)
4.8/5
(39)
The Project Implementation Profile does NOT contain this critical success factor.
(Multiple Choice)
4.7/5
(48)
At the end of week 20, this project has cost $79,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars. 

(Multiple Choice)
4.8/5
(44)
Project goal setting includes setting a baseline plan, which is predicated on:
(Multiple Choice)
4.7/5
(36)
In the build-up stage of a successful project, it is important that:
(Multiple Choice)
4.8/5
(46)
The earned value to date divided by the planned value of work scheduled to be performed is the:
(Multiple Choice)
4.8/5
(37)
Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks. 

(Multiple Choice)
4.9/5
(35)
The project costs plotted against the elapsed time in weeks is known as the __________.
(Short Answer)
4.7/5
(33)
The one factor that earned value management considers that an S-curve does not include is performance.
(True/False)
4.9/5
(38)
If significant deviations from the project plan are detected, corrective action is taken and then:
(Multiple Choice)
4.9/5
(37)
Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. 

(Multiple Choice)
4.9/5
(34)
If the actual cost line on an S-curve undercuts the budgeted cost line, the project has a(n) __________ variance.
(Short Answer)
4.8/5
(37)
The Project Implementation Profile includes this critical success factor.
(Multiple Choice)
4.7/5
(40)
In earned value management analysis, the cumulative amount of the budget becomes the:
(Multiple Choice)
4.9/5
(40)
Showing 81 - 98 of 98
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)