Exam 13: Project Evaluation and Control
Exam 1: Introduction: Why Project Management88 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture90 Questions
Exam 3: Project Selection and Portfolio Management95 Questions
Exam 4: Leadership and the Project Manager108 Questions
Exam 5: Scope Management96 Questions
Exam 6: Project Team Building, Conflict, and Negotiation104 Questions
Exam 7: Risk Management95 Questions
Exam 8: Cost Estimation and Budgeting95 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path98 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks90 Questions
Exam 11: Critical Chain Project Scheduling98 Questions
Exam 12: Resource Management79 Questions
Exam 13: Project Evaluation and Control98 Questions
Exam 14: Project Closeout and Termination100 Questions
Select questions type
A project manager can calculate the projected schedule of the project to completion by using the:
(Multiple Choice)
4.9/5
(34)
Which of these tools allows a project team to make future projections of project status based on its current state?
(Multiple Choice)
4.8/5
(31)
Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds). 

(Multiple Choice)
4.7/5
(37)
Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. 

(Multiple Choice)
4.8/5
(42)
Five weeks in the semester you have completed 0% of your project management class under the 0/100 rule.
(True/False)
4.8/5
(43)
Knowing the correct steps to take once problems develop is a function of a team's:
(Multiple Choice)
4.7/5
(39)
An unmotivated team is a key success inhibitor in every project stage with the exception of the:
(Multiple Choice)
4.7/5
(42)
Earned value management allows a project manager to monitor the project's __________, __________, and __________.
(Short Answer)
4.8/5
(40)
Once an activity has been started it is immediately valued at 50% completed under the __________.
(Short Answer)
4.8/5
(31)
Take the factors considered by earned value analysis and subtract those considered by project S-curves. The factor(s) you have remaining are:
(Multiple Choice)
4.8/5
(33)
A(n) __________ identifies the stage of completion of each task has attained by a specified date within the project.
(Short Answer)
5.0/5
(43)
Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement. 

(Multiple Choice)
4.9/5
(33)
Sketch the project control cycle and discuss the activities that take place in each step.
(Essay)
4.8/5
(40)
The __________ allows the project manager to calculate the project's budget to completion.
(Short Answer)
4.8/5
(40)
The critical success factor that relates to the underlying purpose for the project is the:
(Multiple Choice)
4.8/5
(38)
Showing 21 - 40 of 98
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)