Exam 13: Project Evaluation and Control

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

A project manager can calculate the projected schedule of the project to completion by using the:

(Multiple Choice)
4.9/5
(34)

Which of these tools allows a project team to make future projections of project status based on its current state?

(Multiple Choice)
4.8/5
(31)

Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds). Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds).

(Multiple Choice)
4.7/5
(37)

Use the data to calculate the earned value for the project. All amounts are in thousands of dollars. Use the data to calculate the earned value for the project. All amounts are in thousands of dollars.

(Multiple Choice)
4.8/5
(42)

Five weeks in the semester you have completed 0% of your project management class under the 0/100 rule.

(True/False)
4.8/5
(43)

Knowing the correct steps to take once problems develop is a function of a team's:

(Multiple Choice)
4.7/5
(39)

An S-curve CANNOT be used to:

(Multiple Choice)
4.9/5
(32)

Planned value is:

(Multiple Choice)
5.0/5
(32)

An unmotivated team is a key success inhibitor in every project stage with the exception of the:

(Multiple Choice)
4.7/5
(42)

Earned value management allows a project manager to monitor the project's __________, __________, and __________.

(Short Answer)
4.8/5
(40)

Once an activity has been started it is immediately valued at 50% completed under the __________.

(Short Answer)
4.8/5
(31)

Take the factors considered by earned value analysis and subtract those considered by project S-curves. The factor(s) you have remaining are:

(Multiple Choice)
4.8/5
(33)

A(n) __________ identifies the stage of completion of each task has attained by a specified date within the project.

(Short Answer)
5.0/5
(43)

Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement. Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement.

(Multiple Choice)
4.9/5
(33)

A tracking Gantt chart does NOT show:

(Multiple Choice)
4.9/5
(38)

The budget variance is calculated as:

(Multiple Choice)
4.8/5
(35)

Sketch the project control cycle and discuss the activities that take place in each step.

(Essay)
4.8/5
(40)

The __________ allows the project manager to calculate the project's budget to completion.

(Short Answer)
4.8/5
(40)

Milestones are generally considered to be:

(Multiple Choice)
4.8/5
(44)

The critical success factor that relates to the underlying purpose for the project is the:

(Multiple Choice)
4.8/5
(38)