Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

The best approach to network representation of a large and hugely complex project is to:

(Multiple Choice)
4.8/5
(49)

Use the Gantt chart and the activity list to determine which resource is used the least. Use the Gantt chart and the activity list to determine which resource is used the least.    Use the Gantt chart and the activity list to determine which resource is used the least.

(Multiple Choice)
4.8/5
(38)

In order to accelerate completion of a project, the manager must crash critical path activities.

(True/False)
4.8/5
(30)

An activity on an arrow network:

(Multiple Choice)
4.9/5
(29)

The critical path of this network is: The critical path of this network is:

(Multiple Choice)
4.7/5
(36)

One reason for crashing a project is:

(Multiple Choice)
4.8/5
(32)

Sketch a network and use it as an example as you discuss the four different logical relationships between activities.

(Essay)
4.8/5
(36)

Use the Gantt chart and activity list to determine which resource has the greatest continual use. Use the Gantt chart and activity list to determine which resource has the greatest continual use.    Use the Gantt chart and activity list to determine which resource has the greatest continual use.

(Multiple Choice)
4.8/5
(39)

When involved in a project involving many subcontractors:

(Multiple Choice)
4.9/5
(41)

Networks would not be well suited for:

(Multiple Choice)
4.7/5
(39)

An AOA network:

(Multiple Choice)
4.9/5
(36)

How might a project manager alter a straightforward PERT network to accommodate an inordinately large and complex project?

(Essay)
4.9/5
(51)

Activities A and B have a finish to finish relationship and early start and finish times as shown. What is the result of incorporating a 4 day lag between activities C and B? Activities A and B have a finish to finish relationship and early start and finish times as shown. What is the result of incorporating a 4 day lag between activities C and B?

(Multiple Choice)
4.9/5
(36)

Use the Gantt chart and the activity list to determine which resource is needed earliest in this project. Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.

(Multiple Choice)
4.7/5
(41)

An activity of duration zero whose sole purpose is to maintain network logic is a(n) __________.

(Short Answer)
4.8/5
(41)

A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week. In order to complete this activity within 10 weeks, you must hire additional general laborers at a cost of $2,000 per week. What is the slope for this activity?

(Multiple Choice)
4.8/5
(29)

Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis. How much slack is available in The Great Hair Washing project? Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis. How much slack is available in The Great Hair Washing project?

(Multiple Choice)
5.0/5
(33)

Use the information in the table to create a baseline Gantt chart for the project where activity lengths are given in days. Use the information in the table to create a baseline Gantt chart for the project where activity lengths are given in days.

(Short Answer)
4.7/5
(44)

What is the cost to finish this project (all activity durations are in weeks and costs in US dollars) as quickly as possible? What is the cost to finish this project (all activity durations are in weeks and costs in US dollars) as quickly as possible?

(Essay)
4.9/5
(45)

What is project crashing and what are three reasons why it might be important to do so?

(Essay)
4.8/5
(39)
Showing 21 - 40 of 90
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)