Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks
Exam 1: Introduction: Why Project Management88 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture90 Questions
Exam 3: Project Selection and Portfolio Management95 Questions
Exam 4: Leadership and the Project Manager108 Questions
Exam 5: Scope Management96 Questions
Exam 6: Project Team Building, Conflict, and Negotiation104 Questions
Exam 7: Risk Management95 Questions
Exam 8: Cost Estimation and Budgeting95 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path98 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks90 Questions
Exam 11: Critical Chain Project Scheduling98 Questions
Exam 12: Resource Management79 Questions
Exam 13: Project Evaluation and Control98 Questions
Exam 14: Project Closeout and Termination100 Questions
Select questions type
The best approach to network representation of a large and hugely complex project is to:
(Multiple Choice)
4.8/5
(49)
Use the Gantt chart and the activity list to determine which resource is used the least.



(Multiple Choice)
4.8/5
(38)
In order to accelerate completion of a project, the manager must crash critical path activities.
(True/False)
4.8/5
(30)
Sketch a network and use it as an example as you discuss the four different logical relationships between activities.
(Essay)
4.8/5
(36)
Use the Gantt chart and activity list to determine which resource has the greatest continual use.



(Multiple Choice)
4.8/5
(39)
How might a project manager alter a straightforward PERT network to accommodate an inordinately large and complex project?
(Essay)
4.9/5
(51)
Activities A and B have a finish to finish relationship and early start and finish times as shown. What is the result of incorporating a 4 day lag between activities C and B? 

(Multiple Choice)
4.9/5
(36)
Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.



(Multiple Choice)
4.7/5
(41)
An activity of duration zero whose sole purpose is to maintain network logic is a(n) __________.
(Short Answer)
4.8/5
(41)
A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week. In order to complete this activity within 10 weeks, you must hire additional general laborers at a cost of $2,000 per week. What is the slope for this activity?
(Multiple Choice)
4.8/5
(29)
Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis. How much slack is available in The Great Hair Washing project? 

(Multiple Choice)
5.0/5
(33)
Use the information in the table to create a baseline Gantt chart for the project where activity lengths are given in days.


(Short Answer)
4.7/5
(44)
What is the cost to finish this project (all activity durations are in weeks and costs in US dollars) as quickly as possible?


(Essay)
4.9/5
(45)
What is project crashing and what are three reasons why it might be important to do so?