Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000. Due to slippage on the critical path you need to reduce this activity by three weeks. If the subcontractor informs you that the activity can be completed in 15 weeks for $200,000, what is the slope for the activity?

(Multiple Choice)
4.9/5
(33)

The process of accelerating a project is referred to as __________.

(Short Answer)
4.9/5
(32)

Which statement about this Gantt chart is best? Which statement about this Gantt chart is best?

(Multiple Choice)
4.9/5
(41)

Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest. Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.

(Multiple Choice)
4.9/5
(36)

Determine early start and early finish times for all activities in this network. Activity duration in days appears under each arrow. Determine early start and early finish times for all activities in this network. Activity duration in days appears under each arrow.

(Essay)
4.9/5
(39)

__________ represent one of the first attempts to develop a network diagram that orders project activities by baseline calendar dates.

(Short Answer)
4.9/5
(35)

Finish to start lags are the same as additional activity slack.

(True/False)
4.8/5
(39)

The primary drawback with __________ networks occurs when the project is very complex, with numerous paths through the model.

(Short Answer)
4.8/5
(32)

The process of accelerating a project is referred to as:

(Multiple Choice)
4.8/5
(36)

A finish to start lag delay is usually shown:

(Multiple Choice)
4.8/5
(33)

Use the Gantt chart and activity list to determine which resource is used the most. Use the Gantt chart and activity list to determine which resource is used the most.    Use the Gantt chart and activity list to determine which resource is used the most.

(Multiple Choice)
4.9/5
(37)

Research has shown that, in general,:

(Multiple Choice)
4.9/5
(36)

Use the Gantt chart and activity list to determine which resource is used the least. Use the Gantt chart and activity list to determine which resource is used the least.    Use the Gantt chart and activity list to determine which resource is used the least.

(Multiple Choice)
4.9/5
(40)

What are four criticisms and caveats to bear in mind as you develop a project activity network?

(Essay)
4.8/5
(40)

Given the cost information in the table, what is the cheapest activity to crash on a per week basis? Given the cost information in the table, what is the cheapest activity to crash on a per week basis?

(Multiple Choice)
4.7/5
(43)

A complex project that is managed using a top-down, bottom-up approach to network diagrams means that:

(Multiple Choice)
4.8/5
(40)

The horizontal axis for a Gantt chart is __________.

(Short Answer)
4.9/5
(32)

If a project is extraordinarily complex, rather than showing every possible path through the network and every activity sequence, a(n) __________ that shows only the key subroutines or network paths can be created.

(Short Answer)
4.7/5
(34)

A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks. What is the lowest total cost for completing this project? A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks. What is the lowest total cost for completing this project?

(Multiple Choice)
4.8/5
(33)

If an activity's cost is plotted against its duration on axes with zeros at the origin:

(Multiple Choice)
4.8/5
(41)
Showing 41 - 60 of 90
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)