Exam 6: Defining Scope and Constructing Work Breakdown Structures (WBS)

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Scope planning is the process of creating a project scope statement.

(True/False)
4.9/5
(26)

The project scope planning processes include all of the following EXCEPT:

(Multiple Choice)
4.7/5
(32)

It is important to assign a unique number to every component in the project Work Breakdown Structure.

(True/False)
4.9/5
(32)

In order to construct a project Work Breakdown Structure,a project team needs to enlist support from subject matter experts who understand how each portion of the work will be accomplished.

(True/False)
4.9/5
(40)

The project scope refers to the features and functions that characterize a product,service or result.

(True/False)
4.8/5
(41)

The Work Breakdown Structure is normally developed by listing major deliverables and then progressively smaller ones.

(True/False)
4.8/5
(45)

Almost all projects have deliverables related to training,service or other means of helping the customer to use the project's product effectively.

(True/False)
4.9/5
(41)

If a problem occurs during project execution,the Work Breakdown Structure can be used to understand exactly where and why the problem occurred.

(True/False)
4.8/5
(32)

All of the following conventions are widely adopted when project teams create the second level of the project Work Breakdown Structure (WBS)EXCEPT:

(Multiple Choice)
4.8/5
(37)

Which of the following statements is true concerning the adoption of rolling wave planning in project management?

(Multiple Choice)
4.8/5
(28)

A Work Breakdown Structure (WBS)component is a term that simply refers to an entry in the WBS that can be at any level.

(True/False)
4.9/5
(44)

Each potential change to a project is normally documented by some sort of change request.

(True/False)
4.8/5
(38)

Failure to include project management in the Work Breakdown Structure will increase the likelihood that the project will finish late or over budget.

(True/False)
4.9/5
(38)

Formally documented procedures that define how project deliverables and documentation will be controlled,changed and approved are collectively known by which of the following terms?

(Multiple Choice)
4.9/5
(34)

The best project scope statements are brief,succinct and limit their focus specifically to the work to be performed.

(True/False)
4.9/5
(23)

A thorough scope definition process will often yield multiple project deliverables including intermediate project deliverables due before the project is complete.

(True/False)
4.9/5
(30)

Since work packages provide the basis for future project planning activities,they should be as detailed as possible.

(True/False)
4.8/5
(36)

Subject matter experts can provide invaluable assistance to a project team as it develops a Work Breakdown Structure (WBS). All of the following statements accurately describe the use of subject matter experts in this context EXCEPT:

(Multiple Choice)
4.8/5
(35)

Organizing the second level of the Work Breakdown Structure by major design components facilitates rolling wave planning.

(True/False)
4.8/5
(41)

Work Breakdown Structures can be displayed in a variety of formats including which of the following?

(Multiple Choice)
4.7/5
(39)
Showing 21 - 40 of 45