Exam 7: Scheduling Activities

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

  Figure 7-6 Network Scheduling Data -Consider the network scheduling data provided in Figure 7-6. What is the expected duration of this project? Figure 7-6 Network Scheduling Data -Consider the network scheduling data provided in Figure 7-6. What is the expected duration of this project?

Free
(Multiple Choice)
4.8/5
(41)
Correct Answer:
Verified

C

  Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3. Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date? Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3. Based on the information provided,how many days can you delay the purchase of software (Activity C),without impacting the expected project completion date?

Free
(Multiple Choice)
4.9/5
(46)
Correct Answer:
Verified

B

A scheduled activity that determines when a logical successor activity can begin and end is known as:

Free
(Multiple Choice)
5.0/5
(36)
Correct Answer:
Verified

B

All of the following statements correctly describe an advantage or disadvantage associated with the use of Monte Carlo Analysis EXCEPT:

(Multiple Choice)
4.7/5
(32)

Faced with significant schedule challenges,the project manager has several responsibilities. All of the following are among the project manager's responsibilities EXCEPT:

(Multiple Choice)
4.8/5
(37)

  Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2. Based on the information provided,what is the late start date for activity C - Review Reports? Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2. Based on the information provided,what is the late start date for activity C - "Review Reports"?

(Multiple Choice)
4.8/5
(41)

Milestones are important points in a project schedule that can serve as check points for project managers and sponsors. All of the following reasons might justify the decision to establish a milestone EXCEPT:

(Multiple Choice)
4.9/5
(39)

The enumeration method of determining the critical path relies upon identification of all paths through the project network.

(True/False)
4.8/5
(34)

Monte Carlo Analysis is a technique that computes activity durations based on three time estimates: one optimistic,one pessimistic and one most likely.

(True/False)
4.7/5
(45)

Even small delays on "near-critical" activities can change the critical path of a project.

(True/False)
4.9/5
(42)

The primary advantage of PERT is that it removes uncertainty from the estimates of activity durations,thereby increasing confidence in the reliability of a project schedule.

(True/False)
4.7/5
(40)

The length of time to perform an activity is often dependent upon who will do that work.

(True/False)
4.9/5
(33)

The total number of work periods (not including holidays or other non-work time)required to complete a schedule activity is known as:

(Multiple Choice)
4.9/5
(32)

The first process in developing a project schedule is to identify all the resources available to work on the project.

(True/False)
4.8/5
(38)

  Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3. Based on the information provided,what is the expected duration of this project? Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3. Based on the information provided,what is the expected duration of this project?

(Multiple Choice)
4.9/5
(27)

  Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4. Based on the information provided,identify the critical path(s)for this project? Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4. Based on the information provided,identify the critical path(s)for this project?

(Multiple Choice)
4.9/5
(38)

While the lowest level of decomposition in a Work Breakdown Structure is the work package,work packages can still be decomposed further into project activities.

(True/False)
4.7/5
(31)

The sequencing of activities is often based upon dependencies between the activities. The dependencies that should guide activity sequencing can be either:

(Multiple Choice)
4.8/5
(41)

Which of the following remedies may reduce the likelihood of omissions when developing activity duration estimates?

(Multiple Choice)
4.8/5
(32)

  Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4. Based on the information provided,what is the expected duration of this project? Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4. Based on the information provided,what is the expected duration of this project?

(Multiple Choice)
4.8/5
(45)
Showing 1 - 20 of 56