Exam 6: Defining Scope and Constructing Work Breakdown Structures (WBS)
When developing a Work Breakdown Structure (WBS)for a project,your team can organize the second level elements by project phase,design components or work functions. Describe how these approaches differ. What advantages are associated with each?
When developing a Work Breakdown Structure (WBS) for a project, there are various approaches that your team can use to organize the second level elements. These approaches include organizing by project phase, design components, or work functions. Each approach has its own distinct characteristics and advantages.
Organizing by project phase involves breaking down the project into different stages or phases, such as initiation, planning, execution, monitoring, and closure. This approach allows the team to focus on the specific activities and deliverables that are associated with each phase. It helps in ensuring that all necessary tasks are accounted for and completed in the appropriate sequence. The advantage of organizing by project phase is that it provides a clear roadmap for the project, making it easier to manage and track progress.
Organizing by design components involves breaking down the project into its various components or subsystems. This approach allows the team to focus on the specific technical and functional aspects of the project. It helps in ensuring that all design requirements and specifications are met for each component. The advantage of organizing by design components is that it allows for a more detailed and in-depth analysis of the project, leading to a better understanding of the technical complexities involved.
Organizing by work functions involves breaking down the project into different work packages or tasks based on the specific functions or roles required. This approach allows the team to focus on the specific skills and resources needed for each task. It helps in ensuring that the right people are assigned to the right tasks. The advantage of organizing by work functions is that it helps in optimizing the allocation of resources and maximizing efficiency.
In conclusion, each approach to organizing the second level elements in a WBS has its own advantages. Organizing by project phase provides a clear roadmap for the project, organizing by design components allows for a detailed analysis of the technical aspects, and organizing by work functions helps in optimizing resource allocation. Depending on the nature of the project, a combination of these approaches may be used to create a comprehensive and effective WBS.
Describe the essential elements of a project scope statement as well as the approach you would adopt to prepare one.
A project scope statement is a crucial document that outlines the project's deliverables, objectives, and the work required to complete the project. It serves as a roadmap for the project team and stakeholders, providing a clear understanding of what the project will accomplish and what it will not.
The essential elements of a project scope statement include:
1. Project Objectives: Clearly defined goals and outcomes that the project aims to achieve.
2. Deliverables: Specific products, services, or results that will be produced as a result of the project.
3. Inclusions: The specific work and activities that will be included in the project scope.
4. Exclusions: The work and activities that will not be included in the project scope.
5. Constraints: Any limitations or restrictions that may impact the project, such as budget, resources, or time.
6. Assumptions: Factors or conditions that are believed to be true, but have not been confirmed.
7. Stakeholder Roles and Responsibilities: Identification of key stakeholders and their roles in the project.
To prepare a project scope statement, I would adopt the following approach:
1. Define the project objectives: I would start by clearly defining the project's goals and outcomes, ensuring that they are specific, measurable, achievable, relevant, and time-bound (SMART).
2. Identify deliverables: I would work with the project team and stakeholders to identify the specific products, services, or results that the project will deliver.
3. Gather requirements: I would gather and analyze the requirements for the project, ensuring that all necessary work and activities are included in the scope.
4. Identify constraints and assumptions: I would identify any limitations or restrictions that may impact the project, as well as any factors or conditions that are believed to be true but have not been confirmed.
5. Engage stakeholders: I would engage key stakeholders to ensure that their roles and responsibilities are clearly defined and understood.
6. Review and finalize: I would review the project scope statement with the project team and stakeholders to ensure that it accurately reflects the project's objectives and requirements. Once finalized, the project scope statement would serve as a guiding document throughout the project's lifecycle, helping to ensure that the project stays on track and delivers the intended results.
A deliverable at the lowest level of each branch of a work breakdown structure is known as:
B
Which of the following statements concerning work packages is NOT correct?
The project scope statement will frequently state what is excluded from the project in addition to stating what is included.
All of the following statements correctly describe a contemporary approach to create the Work Breakdown Structure (WBS)for a project EXCEPT:
All of the following elements should be included in a project scope statement EXCEPT:
By using a systematic process of creating a Work Breakdown Structure,project team members can help to ensure they remember all major portions of work to be accomplished.
For each component in the Work Breakdown Structure (WBS),the WBS dictionary includes:
Work Breakdown Structures typically include one or more intermediate levels. Which of the following statements correctly describe the nature of these intermediate levels?
The work package provides the basis for future project planning activities including all of the following EXCEPT:
Almost all projects have deliverables dealing with documentation and customer enablement in addition to the primary deliverable.
The project scope is the work that must be performed to deliver a product,service or result.
Which of the following items best describe the process steps to construct a Work Breakdown Structure (WBS)?
A typical change request form will include which of the following content items?
The Work Breakdown Structure (WBS)is a framework that will be used as a basis for further planning activities including all the following EXCEPT:
What is "scope creep"? What actions can a project manager take to avoid and control scope creep on his or her project?
A WBS dictionary is a document that defines each of the terms used in the project scope statement.
A Work Breakdown Structure must be decomposed at least four levels in order to be effective.
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)