Prioritizing projects and carefully authorizing the start of non-critical activities can serve as remedies for multi-tasking.

(True/False)
4.7/5
(38)

Which of the following responses identifies a common type of logical dependency used to sequence project activities?

(Multiple Choice)
4.9/5
(39)

Projects are often completed late. Describe the techniques you would use as a project manager to improve the accuracy and reliability of your project schedule.

(Essay)
4.9/5
(51)

Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed. All of the following factors can limit how fast a project can be scheduled and completed EXCEPT:

(Multiple Choice)
4.9/5
(31)

  Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3. Based on the information provided,which activities constitute the critical path for this project? Figure 7-3 System Integration Project -Consider the System Integration Project depicted in Figure 7-3. Based on the information provided,which activities constitute the critical path for this project?

(Multiple Choice)
4.9/5
(44)

  Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4. Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date? Figure 7-4 Lab Experiment Project -Consider the Lab Experiment Project depicted in Figure 7-4. Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date?

(Multiple Choice)
4.9/5
(39)

The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish".

(True/False)
4.7/5
(35)

If a project manager delays the start of an activity on the critical path,then the expected completion date of the project will occur at a later date than originally planned.

(True/False)
4.9/5
(35)

The total amount of time a schedule activity may be delayed from its early start date without delaying the project finish date is known as:

(Multiple Choice)
4.9/5
(36)

There is often terrific pressure to complete a project as quickly as possible. To confront this pressure,a project manager should quickly promise to meet the deadlines requested by the sponsor and then assemble a team to create the corresponding schedule.

(True/False)
4.9/5
(44)

GANTT refers to the Generalized Activity Network Tracking Technique which was developed to better understand how variability in the duration of individual activities impacts the expected project duration.

(True/False)
4.8/5
(32)

  Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2. Based on the information provided,which activity can you delay by one day without impacting the expected completion date for the project? Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2. Based on the information provided,which activity can you delay by one day without impacting the expected completion date for the project?

(Multiple Choice)
4.9/5
(33)

Estimating the number of work periods that will be needed to complete individual schedule activities characterizes which of the following time management processes?

(Multiple Choice)
4.9/5
(40)

Which of the following statements correctly describes the critical path?

(Multiple Choice)
4.8/5
(35)

  Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2. Based on the information provided,what is the late start date for activity A - Plan Research? Figure 7-2 Research Project -Consider the Research Project depicted in Figure 7-2. Based on the information provided,what is the late start date for activity A - "Plan Research"?

(Multiple Choice)
4.9/5
(34)

  Figure 7-6 Network Scheduling Data -Consider the network scheduling data provided in Figure 7-6. Which activities constitute the critical path for this project network? Figure 7-6 Network Scheduling Data -Consider the network scheduling data provided in Figure 7-6. Which activities constitute the critical path for this project network?

(Multiple Choice)
4.8/5
(34)

In order for activities to be useful as schedule building blocks,they should have tangible output that can be verified.

(True/False)
4.9/5
(33)

A successor activity follows a predecessor activity based on their logical relationship.

(True/False)
4.7/5
(30)

  Figure 7-5 Duration Estimates -Consider the activity duration estimates presented in Figure 7-5. Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - Package Item? Figure 7-5 Duration Estimates -Consider the activity duration estimates presented in Figure 7-5. Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - "Package Item"?

(Multiple Choice)
5.0/5
(34)

When developing a project schedule,float (or slack)refers to the time between the start and the finish of a planned activity.

(True/False)
4.9/5
(40)