Exam 7: Scheduling Activities
Exam 1: Introduction to Project Management47 Questions
Exam 2: Project Selection and Prioritization51 Questions
Exam 3: Organizational Capability: Structure,Culture and Roles51 Questions
Exam 4: Chartering Projects39 Questions
Exam 5: Stakeholder Analysis and Communication Planning46 Questions
Exam 6: Defining Scope and Constructing Work Breakdown Structures (WBS)45 Questions
Exam 7: Scheduling Activities56 Questions
Exam 8: Resourcing Projects45 Questions
Exam 9: Budgeting Projects47 Questions
Exam 10: Project Risk Planning45 Questions
Exam 11: Project Quality Planning and Project Kick: off46 Questions
Exam 12: Project Supply Chain Management45 Questions
Exam 13: Leading and Managing Project Teams47 Questions
Exam 14: Determining Project Progress and Results45 Questions
Exam 15: Finishing the Project30 Questions
Select questions type
Prioritizing projects and carefully authorizing the start of non-critical activities can serve as remedies for multi-tasking.
(True/False)
4.7/5
(38)
Which of the following responses identifies a common type of logical dependency used to sequence project activities?
(Multiple Choice)
4.9/5
(39)
Projects are often completed late. Describe the techniques you would use as a project manager to improve the accuracy and reliability of your project schedule.
(Essay)
4.9/5
(51)
Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed. All of the following factors can limit how fast a project can be scheduled and completed EXCEPT:
(Multiple Choice)
4.9/5
(31)
Figure 7-3 System Integration Project
-Consider the System Integration Project depicted in Figure 7-3. Based on the information provided,which activities constitute the critical path for this project?

(Multiple Choice)
4.9/5
(44)
Figure 7-4 Lab Experiment Project
-Consider the Lab Experiment Project depicted in Figure 7-4. Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B),without impacting the expected project completion date?

(Multiple Choice)
4.9/5
(39)
The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish".
(True/False)
4.7/5
(35)
If a project manager delays the start of an activity on the critical path,then the expected completion date of the project will occur at a later date than originally planned.
(True/False)
4.9/5
(35)
The total amount of time a schedule activity may be delayed from its early start date without delaying the project finish date is known as:
(Multiple Choice)
4.9/5
(36)
There is often terrific pressure to complete a project as quickly as possible. To confront this pressure,a project manager should quickly promise to meet the deadlines requested by the sponsor and then assemble a team to create the corresponding schedule.
(True/False)
4.9/5
(44)
GANTT refers to the Generalized Activity Network Tracking Technique which was developed to better understand how variability in the duration of individual activities impacts the expected project duration.
(True/False)
4.8/5
(32)
Figure 7-2 Research Project
-Consider the Research Project depicted in Figure 7-2. Based on the information provided,which activity can you delay by one day without impacting the expected completion date for the project?

(Multiple Choice)
4.9/5
(33)
Estimating the number of work periods that will be needed to complete individual schedule activities characterizes which of the following time management processes?
(Multiple Choice)
4.9/5
(40)
Which of the following statements correctly describes the critical path?
(Multiple Choice)
4.8/5
(35)
Figure 7-2 Research Project
-Consider the Research Project depicted in Figure 7-2. Based on the information provided,what is the late start date for activity A - "Plan Research"?

(Multiple Choice)
4.9/5
(34)
Figure 7-6 Network Scheduling Data
-Consider the network scheduling data provided in Figure 7-6. Which activities constitute the critical path for this project network?

(Multiple Choice)
4.8/5
(34)
In order for activities to be useful as schedule building blocks,they should have tangible output that can be verified.
(True/False)
4.9/5
(33)
A successor activity follows a predecessor activity based on their logical relationship.
(True/False)
4.7/5
(30)
Figure 7-5 Duration Estimates
-Consider the activity duration estimates presented in Figure 7-5. Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - "Package Item"?

(Multiple Choice)
5.0/5
(34)
When developing a project schedule,float (or slack)refers to the time between the start and the finish of a planned activity.
(True/False)
4.9/5
(40)