Exam 7: Scheduling Activities
Exam 1: Introduction to Project Management47 Questions
Exam 2: Project Selection and Prioritization51 Questions
Exam 3: Organizational Capability: Structure,Culture and Roles51 Questions
Exam 4: Chartering Projects39 Questions
Exam 5: Stakeholder Analysis and Communication Planning46 Questions
Exam 6: Defining Scope and Constructing Work Breakdown Structures (WBS)45 Questions
Exam 7: Scheduling Activities56 Questions
Exam 8: Resourcing Projects45 Questions
Exam 9: Budgeting Projects47 Questions
Exam 10: Project Risk Planning45 Questions
Exam 11: Project Quality Planning and Project Kick: off46 Questions
Exam 12: Project Supply Chain Management45 Questions
Exam 13: Leading and Managing Project Teams47 Questions
Exam 14: Determining Project Progress and Results45 Questions
Exam 15: Finishing the Project30 Questions
Select questions type
Despite the insights that PERT provides,there are still practical limitations that impact its usefulness. All of the following difficulties are associated with the use of PERT EXCEPT:
(Multiple Choice)
4.9/5
(34)
Figure 7-1 Assembly Project
-Consider the Assembly Project depicted in Figure 7-1. Based on the information provided,what is the early start date for activity D - "Attach Modules 1 & 2"?

(Multiple Choice)
4.8/5
(33)
All of the following strategies can help a project team to develop realistic time estimates for project activities EXCEPT:
(Multiple Choice)
4.9/5
(37)
Figure 7-2 Research Project
-Consider the Research Project depicted in Figure 7-2. Based on the information provided,what is the slack associated with activity C - "Review Reports"?

(Multiple Choice)
4.8/5
(45)
All of the following items can provide useful assistance to a project team to define the activities of a project EXCEPT:
(Multiple Choice)
4.8/5
(37)
All of the following problems contribute to difficulty in estimating activity durations accurately EXCEPT:
(Multiple Choice)
4.8/5
(35)
Figure 7-6 Network Scheduling Data
-Consider the network scheduling data presented in Figure 7-6. How many days of slack are associated with activity F?

(Multiple Choice)
4.8/5
(37)
PERT refers to the Program Evaluation and Review Technique which was developed to better understand how variability in the duration of individual activities impacts the expected project duration.
(True/False)
4.8/5
(31)
A Gantt chart is a tool that can be used to communicate a project schedule.
(True/False)
4.7/5
(38)
Figure 7-3 System Integration Project
-Consider the System Integration Project depicted in Figure 7-3. Based on the information provided,which activities can be delayed one day without impacting the expected project completion date?

(Multiple Choice)
4.9/5
(40)
Describe "slack" and how you can use slack to your advantage in managing a project.
(Not Answered)
This question doesn't have any answer yet
Except in rare circumstances,project teams should not attempt to decompose work packages into project activities because work packages provide sufficient detail to develop a project schedule.
(True/False)
4.7/5
(31)
Figure 7-4 Lab Experiment Project
-Consider the Lab Experiment Project depicted in Figure 7-4. Based on the information provided,which activity can be delayed one day without impacting the expected project completion date?

(Multiple Choice)
4.7/5
(44)
The critical path is the sequence of activities that form the shortest path through the project network and determine the duration of the project.
(True/False)
4.7/5
(39)
The "start-to-start" logical relationship used in activity sequencing applies to the case where initiation of the successor activity depends upon initiation of the predecessor activity.
(True/False)
4.8/5
(39)
Describe how you would use the members of your project team to develop and execute a project schedule.
(Not Answered)
This question doesn't have any answer yet