Exam 8: Cost Estimation and Budgeting
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, structure, and Culture106 Questions
Exam 3: Project Selection and Portfolio Management116 Questions
Exam 4: Leadership and the Project Manager130 Questions
Exam 5: Scope Management116 Questions
Exam 6: Project Team Building, conflict, and Negotiation123 Questions
Exam 7: Risk Management114 Questions
Exam 8: Cost Estimation and Budgeting114 Questions
Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path118 Questions
Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks110 Questions
Exam 11: Critical Chain Project Scheduling117 Questions
Exam 12: Resource Management93 Questions
Exam 13: Project Evaluation and Control117 Questions
Exam 14: Project Closeout and Termination120 Questions
Select questions type
A budget contingency of $1 million on a $10 million project means that the project will be planned for a cost of $10 million,but the project organization receives an extra $1 million to guard against unforeseen cost overruns.
Free
(True/False)
4.7/5
(34)
Correct Answer:
False
Employing an overhead multiplier is sometimes referred to as the ________ rate for direct labor costs.
Free
(Essay)
4.9/5
(40)
Correct Answer:
fully loaded
Activity-based costing and bottom-up budgeting share the step of:
Free
(Multiple Choice)
4.9/5
(28)
Correct Answer:
B
"If anything can go wrong it often will" is an articulation of:
(Multiple Choice)
4.9/5
(45)
Activity-based costing is based on the notion that projects consume activities and activities consume resources.
(True/False)
4.9/5
(35)
Whether it is the Boeing V-22 Osprey or a simple storm door installation for a do-it-yourselfer,nothing is ever completed as quickly or as cheaply as initial estimates due to:
(Multiple Choice)
4.9/5
(35)
A budget that is created by starting with the work breakdown structure,determining costs for each work package,and then adding these costs together is:
(Multiple Choice)
4.8/5
(35)
The unofficial rule of thumb for ________ estimates is to aim for an accuracy of plus or minus 30%.
(Essay)
4.9/5
(28)
Cost estimates that are based as a guideline on real numbers,or figures derived after the completion of preliminary design work,are:
(Multiple Choice)
4.9/5
(38)
Material is an example of a cost that is recurring,variable and direct.
(True/False)
4.8/5
(29)
A common reason for cost overruns in a project is a low initial estimate of project cost.
(True/False)
4.9/5
(32)
What is the total amount budgeted for design costs in this time-phased budget? 

(Multiple Choice)
4.7/5
(35)
What is the cumulative project budget for September in this time-phased budget? 

(Multiple Choice)
4.8/5
(29)
You are probably looking at a bill for a variable cost when you are paying for:
(Multiple Choice)
4.9/5
(38)
What is the cumulative cost in February in this time-phased budget? 

(Multiple Choice)
4.7/5
(33)
An activity with a learning rate of 0.8 takes 30 hours for the first iteration.How long will it take to complete this task for the 12th time?
(Multiple Choice)
4.9/5
(40)
What is the project budget for November in this time-phased budget? 

(Multiple Choice)
4.7/5
(35)
Showing 1 - 20 of 114
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)