Exam 8: Cost Estimation and Budgeting

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

A budget contingency of $1 million on a $10 million project means that the project will be planned for a cost of $10 million,but the project organization receives an extra $1 million to guard against unforeseen cost overruns.

Free
(True/False)
4.7/5
(34)
Correct Answer:
Verified

False

Employing an overhead multiplier is sometimes referred to as the ________ rate for direct labor costs.

Free
(Essay)
4.9/5
(40)
Correct Answer:
Verified

fully loaded

Activity-based costing and bottom-up budgeting share the step of:

Free
(Multiple Choice)
4.9/5
(28)
Correct Answer:
Verified

B

"If anything can go wrong it often will" is an articulation of:

(Multiple Choice)
4.9/5
(45)

Activity-based costing is based on the notion that projects consume activities and activities consume resources.

(True/False)
4.9/5
(35)

Whether it is the Boeing V-22 Osprey or a simple storm door installation for a do-it-yourselfer,nothing is ever completed as quickly or as cheaply as initial estimates due to:

(Multiple Choice)
4.9/5
(35)

A budget that is created by starting with the work breakdown structure,determining costs for each work package,and then adding these costs together is:

(Multiple Choice)
4.8/5
(35)

The unofficial rule of thumb for ________ estimates is to aim for an accuracy of plus or minus 30%.

(Essay)
4.9/5
(28)

Cost estimates that are based as a guideline on real numbers,or figures derived after the completion of preliminary design work,are:

(Multiple Choice)
4.9/5
(38)

Material is an example of a cost that is recurring,variable and direct.

(True/False)
4.8/5
(29)

Contingency money is:

(Multiple Choice)
4.8/5
(35)

What is activity-based costing and how is it performed?

(Essay)
4.8/5
(42)

A common reason for cost overruns in a project is a low initial estimate of project cost.

(True/False)
4.9/5
(32)

What is the total amount budgeted for design costs in this time-phased budget? What is the total amount budgeted for design costs in this time-phased budget?

(Multiple Choice)
4.7/5
(35)

What is the cumulative project budget for September in this time-phased budget? What is the cumulative project budget for September in this time-phased budget?

(Multiple Choice)
4.8/5
(29)

You are probably looking at a bill for a variable cost when you are paying for:

(Multiple Choice)
4.9/5
(38)

What is the cumulative cost in February in this time-phased budget? What is the cumulative cost in February in this time-phased budget?

(Multiple Choice)
4.7/5
(33)

An activity with a learning rate of 0.8 takes 30 hours for the first iteration.How long will it take to complete this task for the 12th time?

(Multiple Choice)
4.9/5
(40)

What is the project budget for November in this time-phased budget? What is the project budget for November in this time-phased budget?

(Multiple Choice)
4.7/5
(35)

What are the major issues with cost estimation of software projects?

(Essay)
4.7/5
(36)
Showing 1 - 20 of 114
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)