Exam 7: Risk Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

With a cost factor of 0.1,a schedule rating of 0.3,a reliability rating of 0.5,and a performance rating of 0.3,the overall consequence of failure was:

Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
Verified

B

If the risk of a negative outcome is slight,the best course of action might be to:

Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
Verified

D

The pointy-haired dean gently suggested that study tour offerings be doubled in the coming three years so Dilbert dutifully explored the possibility of offering a week-long study tour to Elbonia.The globalization committee's consensus was that the probability of failure was high;after some discussion they agreed that the figure was perhaps 0.6.The consequences of failure were another matter.The cost of failure was 0.2,the schedule element was 0.1,and the reliability score was 0.1.The team was divided on what to do with the performance score.Two members were adamant that it was possibly as high as 0.7,but the other two members felt the performance score was closer to the others,in the neighborhood of 0.15.Estimate the overall project risk factor for this undertaking and offer commentary as to the efficacy of the study tour to Elbonia.

Free
(Essay)
4.9/5
(35)
Correct Answer:
Verified

Using the high estimate for the performance score,the overall project risk factor is 0.71.Using the low estimate for the performance score,the overall risk factor is 0.655.The difference between the two values is minimal,although the rule of thumb cutoff of 0.7 puts the high estimate risk category as high and the low estimate at the upper end of the medium risk.Dilbert might be well-served to avoid a study tour to Elbonia.
High Estimate
Cf = (Cc + Cs + Cr + Cp)/4
Cf = (0.2 + 0.1 + 0.1 + 0.7)/4
Cf = 1.1/4 = 0.275
Low Estimate
Cf = (Cc + Cs + Cr + Cp)/4
Cf = (0.2 + 0.1 + 0.1 + 0.15)/4
Cf = 0.55/4 = 0.1375
Overall High
RF = Pf + Cf - PfCf
RF = 0.6 + 0.275 - 0.6 × 0.275
RF = 0.71
Overall Low
RF = Pf + Cf - PfCf
RF = 0.6 + 0.275 - 0.6 × 0.275
RF = 0.655

With the failure probability and consequence scores shown in the table,compute the overall risk factor for the project. With the failure probability and consequence scores shown in the table,compute the overall risk factor for the project.

(Multiple Choice)
4.9/5
(39)

There is always a chance that different entities that should work together to complete a project won't be able to do so.This likelihood is called ________.

(Essay)
4.8/5
(32)

One approach to risk mitigation is simply to accept it.

(True/False)
4.8/5
(29)

Technical risk is the probability that the project will not perform to the required standards or produce substandard products or have excessive operating cost consumption.

(True/False)
4.8/5
(27)

How do mentoring and cross-training mitigate risk?

(Essay)
4.7/5
(33)

The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below.What is the overall risk factor for the project? The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below.What is the overall risk factor for the project?

(Multiple Choice)
4.8/5
(28)

The terpsichorean was familiar with the risks associated with various moves,the accountant knew financial risks forwards and backwards,while the civil engineer could quantify the risks associated with distributed loads on the temporary stage.Their input was used as part of:

(Multiple Choice)
5.0/5
(43)

What are the two types of contingency reserves and how are they handled?

(Essay)
4.8/5
(28)

Risk management is a:

(Multiple Choice)
4.9/5
(30)

A serious risk factor probably has:

(Multiple Choice)
4.8/5
(34)

The expected cost of an item that is estimated at $5,000 with a task contingency multiplier of 1.2 is:

(Multiple Choice)
4.7/5
(28)

The probability that the investments made to fund the front-end activities will be lost due to project abandonment is financing risk.

(True/False)
4.7/5
(28)

Opportunity and risk are at their peak during the ________ phase of the project.

(Essay)
4.7/5
(25)

Project penalty clauses that initiate at mutually agreed-on points in the project's development and implementation are:

(Multiple Choice)
4.9/5
(34)

The budget safety measures that address higher risks than task contingency are known as:

(Multiple Choice)
4.9/5
(38)

The professor wore both a belt and suspenders during lecture each day because he chose to:

(Multiple Choice)
4.8/5
(36)

Opportunity emerges from favorable project circumstances and risk from unfavorable events.

(True/False)
4.9/5
(43)
Showing 1 - 20 of 114