Exam 12: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Integrated change control is a key activity during the monitoring and controlling phase of a project.

(True/False)
4.9/5
(31)

Following are the three time estimates for a task in a project: optimistic completion time = 2 weeks Most likely completion time = 4 weeks Pessimistic completion time = 7 weeks Compute the expected time for the task.

(Multiple Choice)
4.8/5
(40)

Tasks on the critical path with no slack are known as ________.

(Short Answer)
4.7/5
(28)

The phase of the project in which the rate of spending typically increases is the

(Multiple Choice)
4.9/5
(30)

As per the Project risk/return matrix,projects that are poor candidates have a

(Multiple Choice)
4.9/5
(30)

A task in a project which is a critical task should be chosen for crashing.

(True/False)
4.7/5
(28)

It has been estimated that the mean time required to complete a project is 20 weeks and the variance of project completion time is 9 weeks.So there is a 50% chance that the project can be completed in

(Multiple Choice)
4.9/5
(43)

Developing a road map for the project is known as ________.

(Short Answer)
4.8/5
(35)

The process of reporting to see that the project plan is being followed is known as ________.

(Short Answer)
4.8/5
(32)

Integrated change control is a key activity during which phase of a project?

(Multiple Choice)
4.8/5
(27)

________ is a term applied to the process of managing changes to the project charter and plan.

(Short Answer)
5.0/5
(31)

Developing the project management plan is a key activity during which phase of a project?

(Multiple Choice)
4.9/5
(41)

If two consecutive tasks on the same path each have two days of slack,this means that each of them can be delayed by two days without delaying the project.

(True/False)
4.7/5
(38)

The method for planning projects that uses shortest paths is called ________.

(Short Answer)
4.9/5
(35)

The difference between the latest possible completion time and the earliest possible completion time for a project task is known as ________.

(Short Answer)
5.0/5
(43)

A sequence of activities that leads from the starting node to the finishing node is called a

(Multiple Choice)
4.9/5
(27)

The shortest time for completing a project task is known as ________.

(Short Answer)
4.8/5
(35)

The act of determining which tasks precede and follow other tasks is known as ________.

(Short Answer)
4.8/5
(24)

The latest starting time for a task is equal to the latest finish time minus the task time.

(True/False)
4.8/5
(37)

As per Belbin,a person who has the strengths of being an extrovert,enthusiastic,communicative and someone who explores opportunities and develops contacts is ideal for the project team role of

(Multiple Choice)
4.7/5
(33)
Showing 41 - 60 of 90
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)