Exam 12: Project Management
Exam 1: Introduction to Supply Chain and Operations Management89 Questions
Exam 2: Supply Chain and Operations Strategy71 Questions
Exam 3: Product and Process Design and Mapping84 Questions
Exam 4: Service Design97 Questions
Exam 5: Customer Relationship Management60 Questions
Exam 6: Strategic Sourcing78 Questions
Exam 7: Supplier Management64 Questions
Exam 8: Demand Management and Forecasting81 Questions
Exam 9: Inventory Management Fundamentals and Independent Demand84 Questions
Exam 10: Sales and Operations Planning and Enterprise Resource Planning115 Questions
Exam 11: Logistics86 Questions
Exam 12: Project Management90 Questions
Exam 13: Supply Chain Quality Management84 Questions
Exam 14: Statistical Process Control80 Questions
Exam 15: New Section76 Questions
Select questions type
The act of celebrating successes,releasing resources,including people,and performing a project debrief is known as ________.
Free
(Short Answer)
4.8/5
(39)
Correct Answer:
closing a project
The act of leading and directing the people and other resources in a project is known as ________.
Free
(Short Answer)
4.8/5
(27)
Correct Answer:
project management
The shortest time for completing a project task is known as most likely completion time.
Free
(True/False)
4.9/5
(32)
Correct Answer:
False
The act of applying more resources to a project task to reduce its expected completion time is called ________.
(Short Answer)
4.8/5
(35)
The phase of the project in which the rate of spending typically increases is the ________ phase.
(Short Answer)
5.0/5
(41)
In a project network,the critical path is the sequence of activities which has the
(Multiple Choice)
4.7/5
(31)
The path in a network with the shortest length of time to completion is called the critical path.
(True/False)
4.7/5
(28)
The network diagram describes sequential relationships among major tasks on a project.
(True/False)
4.9/5
(45)
Following are the three time estimates for a task in a project: optimistic completion time = 2 weeks
Most likely completion time = 4 weeks
Pessimistic completion time = 7 weeks
Compute the task variance.
(Multiple Choice)
4.9/5
(36)
The scope or participation in a Tiger team usually involves a local or single department.
(True/False)
4.7/5
(23)
A tool for monitoring who is assigned to multiple projects is known as ________.
(Short Answer)
4.8/5
(34)
The project team stage of development when the team becomes a cohesive unit and interdependence,trust,and cooperation develops between team members is
(Multiple Choice)
4.8/5
(31)
A task in a project which takes the longest to complete should be chosen for crashing.
(True/False)
4.7/5
(42)
As per the Project risk/return matrix,projects that are excellent candidates have a
(Multiple Choice)
4.7/5
(33)
A one-time,temporary endeavor with a defined beginning and ending is known as a ________.
(Short Answer)
4.7/5
(39)
A project network in which activities are labeled on the network nodes is known as ________.
(Short Answer)
4.9/5
(31)
A document that outlines the primary deliverables,the objective,and the parameters of a project is known as ________.
(Short Answer)
4.7/5
(35)
As per Hersey and Blanchard's Situation Leadership Model,the manager's role of telling is categorized as
(Multiple Choice)
4.9/5
(41)