Exam 12: Project Management
Exam 1: Introduction to Supply Chain and Operations Management89 Questions
Exam 2: Supply Chain and Operations Strategy71 Questions
Exam 3: Product and Process Design and Mapping84 Questions
Exam 4: Service Design97 Questions
Exam 5: Customer Relationship Management60 Questions
Exam 6: Strategic Sourcing78 Questions
Exam 7: Supplier Management64 Questions
Exam 8: Demand Management and Forecasting81 Questions
Exam 9: Inventory Management Fundamentals and Independent Demand84 Questions
Exam 10: Sales and Operations Planning and Enterprise Resource Planning115 Questions
Exam 11: Logistics86 Questions
Exam 12: Project Management90 Questions
Exam 13: Supply Chain Quality Management84 Questions
Exam 14: Statistical Process Control80 Questions
Exam 15: New Section76 Questions
Select questions type
The standard deviation of the critical path is equal to the sum of the standard deviations of all of the tasks on the critical path.
(True/False)
4.7/5
(34)
Key phases in a project time line are often referred to as milestones.
(True/False)
4.9/5
(35)
Developing the preliminary project scope statement is a key activity during which phase of a project?
(Multiple Choice)
4.8/5
(28)
Developing the project charter is a key activity during which phase of a project?
(Multiple Choice)
4.8/5
(34)
Developing the project charter is a key activity during the planning phase of a project.
(True/False)
4.9/5
(37)
The project team stage of development when the team members get to know each other,however,agreements have not yet been made to facilitate smooth interaction between team members,is
(Multiple Choice)
4.7/5
(31)
The best estimate for the time required to complete a project task is known as ________.
(Short Answer)
4.9/5
(36)
Allowing the deliverables of a project to expand over time is known as ________.
(Short Answer)
4.8/5
(30)
The project planning step of estimating activity times is done before determining the work breakdown structure of a project.
(True/False)
5.0/5
(31)
As per Hersey and Blanchard's Situation Leadership Model,which role of a manager can be described as Low Task Behavior and Low Relationship Behavior?
(Multiple Choice)
4.8/5
(32)
The earliest finish time for a task is equal to the latest finish time minus the task time.
(True/False)
4.8/5
(33)
Task C is directly preceded by two tasks-task A and task B.Task A has an expected task completion time of five weeks and an ES time of week 6.Task B has an expected task completion time of seven weeks and an ES time of week 7.Task C has an expected task completion time of 10 weeks.The ES for activity C is week
(Multiple Choice)
4.9/5
(44)
The project charter is most likely to include the project goals,scope and deliverables.
(True/False)
4.9/5
(30)
Specialists that are assigned full-time to a project that needs to be completed quickly are known as ________ team(s).
(Short Answer)
4.8/5
(40)
The longest foreseeable task completion time is known as pessimistic completion time.
(True/False)
4.9/5
(28)
The formula which helps compute project times with a high probability of completion is known as ________.
(Short Answer)
4.9/5
(41)
An organizational form in which an employee works part-time on a project team and continues to perform fundamental job assignments is known as ________ structure.
(Short Answer)
4.7/5
(37)
Given the portion of the network diagram shown below,where numbers in boxes show the task times,what is the earliest finish time for task C,if the earliest start time for task A is 10,and the earliest start time for task B is 13? 

(Multiple Choice)
4.9/5
(34)
As per the Project risk/return matrix,projects that are low-hanging fruit have a
(Multiple Choice)
4.9/5
(36)