Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain
Exam 1: Introduction: Why Project Management103 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management98 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
ABC project organization has one workstation that is capable of generating the drawings that their clients study before accepting ABC's bid. ABC is currently in the midst of three proposal projects and knows which proposed project will be most profitable and which will be least profitable. The workstation is scheduled so that the most profitable project's work is done first and the least profitable project work is done last. This is an example of:
(Multiple Choice)
4.8/5
(43)
A resource constraint can be exploited using CCPM methodology by:
(Multiple Choice)
4.8/5
(37)
A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in weeks) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project. 

(Multiple Choice)
4.8/5
(32)
When choosing the most viable solution to resource conflict issues, the BEST option is the one that:
(Multiple Choice)
4.8/5
(38)
The waterfall project development process is well-suited for instances where:
(Multiple Choice)
4.7/5
(30)
Use the project information in the table to resolve resource conflicts, identify the critical chain and critical path, and create feeder buffers. A feeder buffer should be placed immediately before: 

(Multiple Choice)
4.9/5
(34)
Subcontractor deliveries are difficult to schedule with the critical chain project methodology because:
(Multiple Choice)
4.8/5
(34)
A project consists of four activities with information as shown in the table. What is the overall variance of the project's duration? 

(Multiple Choice)
4.9/5
(22)
The one element that Agile shares with traditional project management in a software development environment is that all testing is done at the very end of the project.
(True/False)
4.9/5
(28)
A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the feeder buffer for path NQT if this project is managed using critical chain methodology? 

(Multiple Choice)
4.8/5
(35)
A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the overall duration of this project if it is managed using critical chain methodology? 

(Multiple Choice)
4.8/5
(42)
The customers articulate the necessary features of a software project through:
(Multiple Choice)
4.8/5
(47)
An important departure from traditional project management is that critical chain project management logic:
(Multiple Choice)
4.8/5
(44)
Use the project information in the table to resolve resource conflicts, identify the critical chain and critical path, and create feeder buffers. The project buffer follows: 

(Multiple Choice)
4.8/5
(24)
Agile project management is well-suited for the case where requirements change in the middle of project development.
(True/False)
4.9/5
(35)
Use the project information in the table to resolve resource conflicts, identify the critical chain and critical path, and create feeder buffers. The critical chain does NOT pass through: 

(Multiple Choice)
4.8/5
(34)
A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many project buffers are needed if this project is managed using critical chain methodology? 

(Multiple Choice)
4.8/5
(36)
A project that consists of six consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project. How does the project buffer computed this way compare with the estimation for project buffer offered by Goldratt?


(Essay)
4.9/5
(37)
Showing 61 - 80 of 101
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)