Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The Central Limit Theorem says that if a number of probability distributions are summed:

(Multiple Choice)
4.8/5
(32)

Create a 5-activity example and use it to explain the difference between the critical path method and critical chain project management.

(Essay)
4.8/5
(28)

All of these happen during the sprint phase EXCEPT:

(Multiple Choice)
4.9/5
(30)

The critical chain is usually the same as the critical path.

(True/False)
4.8/5
(39)

A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of a feeder buffer if this project is managed using critical chain methodology? A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of a feeder buffer if this project is managed using critical chain methodology?

(Multiple Choice)
4.8/5
(26)

A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the project buffer if this project is managed using critical chain methodology? Use the rule of thumb approach. A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the project buffer if this project is managed using critical chain methodology? Use the rule of thumb approach.

(Multiple Choice)
4.8/5
(25)

A key element of extreme programming is:

(Multiple Choice)
4.8/5
(37)

What is Agile PM and what makes it ideal for many software development projects?

(Essay)
4.8/5
(31)

A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project. A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project.

(Multiple Choice)
4.9/5
(34)

The buffers supplied to non-critical paths in critical chain project management are called:

(Multiple Choice)
4.7/5
(31)

A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the overall duration of this project if it is managed using critical chain methodology? A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the overall duration of this project if it is managed using critical chain methodology?

(Multiple Choice)
4.8/5
(27)

A product backlog is the final list of what is needed to complete the project.

(True/False)
4.8/5
(33)

What is the waterfall planning process and when is the ideal approach to project development?

(Essay)
4.7/5
(32)

The legal department is needed to review all contracts a project organization enters. The legal department is continually swamped with work and all other departments find themselves waiting on legal before they can begin their work. Legal is the drum for this organization.

(True/False)
4.8/5
(38)

A project consists of four activities with information as shown in the table. What is the overall variance of the project? A project consists of four activities with information as shown in the table. What is the overall variance of the project?

(Multiple Choice)
4.8/5
(44)

Which of these numerical (quantity) comparisons is CORRECT?

(Multiple Choice)
4.8/5
(31)

A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project? A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project?

(Multiple Choice)
4.7/5
(34)

What are some arguments against the XP technique of pair programming?

(Essay)
4.8/5
(37)

Which of the following statements about CCPM activity networks is CORRECT?

(Multiple Choice)
4.9/5
(36)

A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of a feeder buffer if this project is managed using critical chain methodology? A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of a feeder buffer if this project is managed using critical chain methodology?

(Multiple Choice)
4.7/5
(37)
Showing 41 - 60 of 101
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)