Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain
Exam 1: Introduction: Why Project Management103 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management98 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
The Central Limit Theorem says that if a number of probability distributions are summed:
(Multiple Choice)
4.8/5
(32)
Create a 5-activity example and use it to explain the difference between the critical path method and critical chain project management.
(Essay)
4.8/5
(28)
A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of a feeder buffer if this project is managed using critical chain methodology? 

(Multiple Choice)
4.8/5
(26)
A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the project buffer if this project is managed using critical chain methodology? Use the rule of thumb approach. 

(Multiple Choice)
4.8/5
(25)
What is Agile PM and what makes it ideal for many software development projects?
(Essay)
4.8/5
(31)
A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project. 

(Multiple Choice)
4.9/5
(34)
The buffers supplied to non-critical paths in critical chain project management are called:
(Multiple Choice)
4.7/5
(31)
A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the overall duration of this project if it is managed using critical chain methodology? 

(Multiple Choice)
4.8/5
(27)
A product backlog is the final list of what is needed to complete the project.
(True/False)
4.8/5
(33)
What is the waterfall planning process and when is the ideal approach to project development?
(Essay)
4.7/5
(32)
The legal department is needed to review all contracts a project organization enters. The legal department is continually swamped with work and all other departments find themselves waiting on legal before they can begin their work. Legal is the drum for this organization.
(True/False)
4.8/5
(38)
A project consists of four activities with information as shown in the table. What is the overall variance of the project? 

(Multiple Choice)
4.8/5
(44)
Which of these numerical (quantity) comparisons is CORRECT?
(Multiple Choice)
4.8/5
(31)
A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project? 

(Multiple Choice)
4.7/5
(34)
What are some arguments against the XP technique of pair programming?
(Essay)
4.8/5
(37)
Which of the following statements about CCPM activity networks is CORRECT?
(Multiple Choice)
4.9/5
(36)
A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of a feeder buffer if this project is managed using critical chain methodology? 

(Multiple Choice)
4.7/5
(37)
Showing 41 - 60 of 101
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)